Strip Footing Calculator (Isolated, Strip & Circular — Volume, Cement, Sand & Aggregate)

Calculate footing concrete volume and materials.

Inputs

ℹ️Isolated/Pad supports a single column. Strip/Continuous runs under a wall or a closely spaced row of columns — same formula as Isolated, just usually a much longer run. Circular/Pier is a round base, common under a single steel column or post.

ℹ️The total length of the continuous wall/column run this footing supports.

Cost

Enable Cost Estimation?

Concrete Volume

2.700/ 95.3 cft

Total Wet Volume: 2.700 m³ / 95.3 cft

Dry Volume: 4.158 m³ / 146.8 cft

Sand: 1.188 m³ / 42.0 cft

Aggregate: 2.376 m³ / 83.9 cft

Cement Required
(Including 5% Wastage)

18 bags

Extra (Wastage): 0.86 bags

Approximate results for planning only. Verify with a professional.

Strip Footing Visualizationrun continues both waysRun Length: 15 mW = 0.6 mT = 300 mmDiagram simplified for clarity (not to scale)

Looking for the verification checklist, reference tables, tips, or common mistakes?See the complete Concrete Footing Calculator.

15 m strip footing, 0.6 m wide x 300 mm thick

A strip (continuous) footing runs under a load-bearing wall or a closely spaced row of columns, so it uses the same Length x Width x Thickness formula as an isolated footing — just over a much longer run. For a 15 m run at 0.6 m wide and 300 mm thick, wet volume is 2.7 m³, dry volume 4.158 m³, needing about 18 cement bags (1:2:4 mix, 5% wastage), 1.188 m³ sand, and 2.376 m³ aggregate.

The calculator is pre-filled for this footing use case. Edit any input and the worked example updates from the active values.

  • Default run: 15 m x 0.6 m wide, 300 mm thick.
  • Same formula as Isolated — L x W x T.
  • ~18 cement bags with 5% wastage (1:2:4 mix).

How does the concrete footing calculator work?

Wet volume depends on the footing shape — Isolated and Strip share the same rectangular formula, while Circular uses the circle area instead. Every shape then follows the same dry-volume, mix-ratio, and wastage steps.

Step 1 — Isolated / Strip (Rectangular)

Wet Volume = Length × Width × Thickness × Count

A Strip footing uses the exact same formula — its "Length" is just a wall run instead of a small pad.

Step 2 — Circular / Pier

Wet Volume = π × (Diameter / 2)² × Thickness × Count

Enter the diameter, not the radius — the formula already halves it.

Step 3 — Convert to Dry Volume

Dry Volume = Wet Volume × 1.54

The 1.54 factor accounts for voids in aggregates, sand bulking, and material loss during mixing.

Step 4 — Split by Mix Ratio

Cement = (Cement Ratio ÷ Total Ratio) × Dry Volume — same for Sand and Aggregate

Step 5 — Convert Cement Volume to Bags

Cement Bags = Cement Volume ÷ 0.0347

Step 6 — Add Wastage

Final Cement Bags = Calculated Bags × (1 + Wastage %)

Step 7 — Cost (Optional)

Total Cost = (Cement Bags × Price/Bag) + (Sand Volume × Price/Volume) + (Aggregate Volume × Price/Volume)

All three quantities are priced at their wastage-adjusted amount — the quantity you'd actually order, not the theoretical minimum before wastage. Sand and aggregate prices can be entered per m³ or per cft — whichever unit you enter is converted to match the volume automatically.

Worked Example

This example uses the active inputs above and follows the same steps as the Formula section.

Input Values Used

InputValue
Footing TypeStrip / Continuous Footing
Run Length15 m (15 m)
Width0.6 m (0.6 m)
Thickness300 mm (0.3 m)
Count1
Concrete MixM15 (1:2:4)
Wastage5%

Step 1 — Wet Volume

CalculationSubstitutionResult
L × W × T × Count15 × 0.6 × 0.3 × 12.7 m³ / 95.3 cft

Step 2 — Dry Volume

CalculationSubstitutionResult
Dry Volume = Wet Volume × 1.542.7 × 1.544.158 m³ / 146.8 cft

Step 3 — Materials & Cement Bags

MaterialShare of Mix (1:2:4)Result
Sand2 / 71.188 m³ / 42.0 cft
Aggregate4 / 72.376 m³ / 83.9 cft
Cement Bags (with 5% wastage)1 / 718 bags

Therefore, this strip / continuous footing needs approximately 2.7 m³ / 95.3 cft of concrete, requiring 18 cement bags, 1.188 m³ / 42.0 cft sand, and 2.376 m³ / 83.9 cft aggregate (including 5% wastage on cement).

Cross-check against the Footing Type & Mix Reference table in the complete Concrete Footing Calculator.

FAQ

Because a strip footing is mathematically just a long, continuous rectangular footing — Volume = Length x Width x Thickness applies exactly the same way, whether Length is a 1.5 m pad or a 15 m wall run. The two are kept as separate Footing Type options because their typical dimensions, labels, and search terms differ, not because the math does.
When a load-bearing wall needs continuous support, or when a row of columns is spaced closely enough that separate isolated footings would overlap or nearly touch — combining them into one continuous strip is simpler to form and often more economical than several adjacent pads.