TryBuildCalc

Footing Concrete Volume Calculator (Isolated, Strip & Circular — Volume, Cement, Sand & Aggregate)

Calculate footing concrete volume and materials.

Inputs

ℹ️Isolated/Pad supports a single column. Strip/Continuous runs under a wall or a closely spaced row of columns — same formula as Isolated, just usually a much longer run. Circular/Pier is a round base, common under a single steel column or post.

ℹ️The plan length of a single footing.

Cost

Enable Cost Estimation?

Showing results for 6 footings

Concrete Volume

6.371/ 225.0 cft

(1.062 m³ / 37.5 cft per footing)

Total Wet Volume: 6.371 m³ / 225.0 cft

Dry Volume: 9.812 m³ / 346.5 cft

Sand: 2.676 m³ / 94.5 cft

Aggregate: 5.352 m³ / 189.0 cft

(Per footing: Sand 0.446 m³ / 15.8 cft, Aggregate 0.892 m³ / 31.5 cft)

Cement Required
(Including 5% Wastage)

54 bags

(9 bags per footing)

Extra (Wastage): 2.57 bags

Approximate results for planning only. Verify with a professional.

Isolated Footing VisualizationL = 5 ftW = 5 ftT = 18 inDiagram simplified for clarity (not to scale)

Looking for the verification checklist, reference tables, tips, or common mistakes?See the complete Concrete Footing Calculator.

Footing concrete volume

This page is useful when footing dimensions are measured in feet and inches.

The calculator is pre-filled for this footing use case. Edit any input and the worked example updates from the active values.

  • Footing size: 5 ft x 5 ft.
  • Thickness: 18 in.
  • Count: 6 footings.

How does the concrete footing calculator work?

Wet volume depends on the footing shape — Isolated and Strip share the same rectangular formula, while Circular uses the circle area instead. Every shape then follows the same dry-volume, mix-ratio, and wastage steps.

Step 1 — Isolated / Strip (Rectangular)

Wet Volume = Length × Width × Thickness × Count

A Strip footing uses the exact same formula — its "Length" is just a wall run instead of a small pad.

Step 2 — Circular / Pier

Wet Volume = π × (Diameter / 2)² × Thickness × Count

Enter the diameter, not the radius — the formula already halves it.

Step 3 — Convert to Dry Volume

Dry Volume = Wet Volume × 1.54

The 1.54 factor accounts for voids in aggregates, sand bulking, and material loss during mixing.

Step 4 — Split by Mix Ratio

Cement = (Cement Ratio ÷ Total Ratio) × Dry Volume — same for Sand and Aggregate

Step 5 — Convert Cement Volume to Bags

Cement Bags = Cement Volume ÷ 0.0347

Step 6 — Add Wastage

Final Cement Bags = Calculated Bags × (1 + Wastage %)

Step 7 — Cost (Optional)

Total Cost = (Cement Bags × Price/Bag) + (Sand Volume × Price/Volume) + (Aggregate Volume × Price/Volume)

All three quantities are priced at their wastage-adjusted amount — the quantity you'd actually order, not the theoretical minimum before wastage. Sand and aggregate prices can be entered per m³ or per cft — whichever unit you enter is converted to match the volume automatically.

Worked Example

This example uses the active inputs above and follows the same steps as the Formula section.

Input Values Used

InputValue
Footing TypeIsolated / Pad Footing
Length5 ft (1.524 m)
Width5 ft (1.524 m)
Thickness18 in (0.4572 m)
Count6
Concrete MixM20 (1:1.5:3)
Wastage5%

Step 1 — Wet Volume

CalculationSubstitutionResult
L × W × T × Count1.524 × 1.524 × 0.4572 × 66.371 m³ / 225.0 cft

Step 2 — Dry Volume

CalculationSubstitutionResult
Dry Volume = Wet Volume × 1.546.371 × 1.549.812 m³ / 346.5 cft

Step 3 — Materials & Cement Bags

MaterialShare of Mix (1:1.5:3)Result
Sand1.5 / 5.52.676 m³ / 94.5 cft
Aggregate3 / 5.55.352 m³ / 189.0 cft
Cement Bags (with 5% wastage)1 / 5.554 bags

Therefore, this isolated / pad footing needs approximately 6.371 m³ / 225.0 cft of concrete, requiring 54 cement bags, 2.676 m³ / 94.5 cft sand, and 5.352 m³ / 189.0 cft aggregate (including 5% wastage on cement).

Cross-check against the Footing Type & Mix Reference table in the complete Concrete Footing Calculator.

FAQ

This page is pre-filled for footing concrete volume calculator so you can estimate footing concrete volume, cement bags, sand, aggregate, and wastage.
Yes — every input on this page is fully editable, including Footing Type, dimensions, and count.