TryBuildCalc

Circular Footing Calculator (Isolated, Strip & Circular — Volume, Cement, Sand & Aggregate)

Calculate footing concrete volume and materials.

Inputs

ℹ️Isolated/Pad supports a single column. Strip/Continuous runs under a wall or a closely spaced row of columns — same formula as Isolated, just usually a much longer run. Circular/Pier is a round base, common under a single steel column or post.

ℹ️Enter the diameter, not the radius — using the radius here would understate volume by a factor of 4.

Cost

Enable Cost Estimation?

Showing results for 4 footings

Concrete Volume

0.942/ 33.3 cft

(0.235 m³ / 8.3 cft per footing)

Total Wet Volume: 0.942 m³ / 33.3 cft

Dry Volume: 1.451 m³ / 51.2 cft

Sand: 0.396 m³ / 14.0 cft

Aggregate: 0.792 m³ / 28.0 cft

(Per footing: Sand 0.099 m³ / 3.5 cft, Aggregate 0.198 m³ / 7.0 cft)

Cement Required
(Including 5% Wastage)

8 bags

(2 bags per footing)

Extra (Wastage): 0.38 bags

Approximate results for planning only. Verify with a professional.

Circular Footing VisualizationD = 1 mT = 300 mmDiagram simplified for clarity (not to scale)

Looking for the verification checklist, reference tables, tips, or common mistakes?See the complete Concrete Footing Calculator.

4 circular piers, 1 m diameter x 300 mm thick

A circular (pier) footing uses Volume = pi x (Diameter/2)^2 x Thickness — a genuinely different formula from a rectangular footing, since it's based on the circle's area rather than length x width. For 4 piers at 1 m diameter and 300 mm thick, total wet volume is 0.942 m³, dry volume 1.451 m³, needing about 8 cement bags (1:1.5:3 mix, 5% wastage), 0.396 m³ sand, and 0.792 m³ aggregate.

The calculator is pre-filled for this footing use case. Edit any input and the worked example updates from the active values.

  • Default: 4 piers, 1 m diameter, 300 mm thick.
  • Formula: pi x (D/2)^2 x T x Count.
  • ~8 cement bags with 5% wastage (1:1.5:3 mix).

How does the concrete footing calculator work?

Wet volume depends on the footing shape — Isolated and Strip share the same rectangular formula, while Circular uses the circle area instead. Every shape then follows the same dry-volume, mix-ratio, and wastage steps.

Step 1 — Isolated / Strip (Rectangular)

Wet Volume = Length × Width × Thickness × Count

A Strip footing uses the exact same formula — its "Length" is just a wall run instead of a small pad.

Step 2 — Circular / Pier

Wet Volume = π × (Diameter / 2)² × Thickness × Count

Enter the diameter, not the radius — the formula already halves it.

Step 3 — Convert to Dry Volume

Dry Volume = Wet Volume × 1.54

The 1.54 factor accounts for voids in aggregates, sand bulking, and material loss during mixing.

Step 4 — Split by Mix Ratio

Cement = (Cement Ratio ÷ Total Ratio) × Dry Volume — same for Sand and Aggregate

Step 5 — Convert Cement Volume to Bags

Cement Bags = Cement Volume ÷ 0.0347

Step 6 — Add Wastage

Final Cement Bags = Calculated Bags × (1 + Wastage %)

Step 7 — Cost (Optional)

Total Cost = (Cement Bags × Price/Bag) + (Sand Volume × Price/Volume) + (Aggregate Volume × Price/Volume)

All three quantities are priced at their wastage-adjusted amount — the quantity you'd actually order, not the theoretical minimum before wastage. Sand and aggregate prices can be entered per m³ or per cft — whichever unit you enter is converted to match the volume automatically.

Worked Example

This example uses the active inputs above and follows the same steps as the Formula section.

Input Values Used

InputValue
Footing TypeCircular / Pier Footing
Diameter1 m (1 m)
Thickness300 mm (0.3 m)
Count4
Concrete MixM20 (1:1.5:3)
Wastage5%

Step 1 — Wet Volume

CalculationSubstitutionResult
π × (D / 2)² × T × Countπ × (1 / 2)² × 0.3 × 40.942 m³ / 33.3 cft

Step 2 — Dry Volume

CalculationSubstitutionResult
Dry Volume = Wet Volume × 1.540.942 × 1.541.451 m³ / 51.2 cft

Step 3 — Materials & Cement Bags

MaterialShare of Mix (1:1.5:3)Result
Sand1.5 / 5.50.396 m³ / 14.0 cft
Aggregate3 / 5.50.792 m³ / 28.0 cft
Cement Bags (with 5% wastage)1 / 5.58 bags

Therefore, this circular / pier footing needs approximately 0.942 m³ / 33.3 cft of concrete, requiring 8 cement bags, 0.396 m³ / 14.0 cft sand, and 0.792 m³ / 28.0 cft aggregate (including 5% wastage on cement).

Cross-check against the Footing Type & Mix Reference table in the complete Concrete Footing Calculator.

FAQ

A circular footing's plan area is a circle (pi x radius^2), not a rectangle (length x width), so its volume formula genuinely differs: Volume = pi x (Diameter/2)^2 x Thickness x Count. This is the one footing shape on this calculator that isn't just a relabeled version of the rectangular formula.
This usually means a radius was used somewhere it shouldn't have been. The formula already divides the diameter by 2 to get the radius internally — if you entered a value that was already a radius (mistaking it for the diameter), the resulting area (and volume) comes out 4x too small. Always enter the full diameter, as dimensioned on the drawing.