TryBuildCalc

UPS / Inverter Battery Capacity Calculator (Runtime & Battery Bank Sizing)

Calculate UPS battery capacity instantly.

Inputs

What do you want to know?

Equipment to Power

Pick a preset for a typical starting point, or choose Custom and enter your equipment's actual nameplate watts.

Equipment 1

W

Equipment 2

W

Equipment 3

W

Battery Configuration

ℹ️Sets the default depth-of-discharge limit — override it below if your manufacturer specifies something different.

%

ℹ️Leave blank to use the selected battery type's recommended default.

V

ℹ️The voltage of ONE battery unit — commonly 6V, 12V, or 2V cells.

Ah
V

ℹ️Your inverter/UPS's DC bus voltage — must be an exact multiple of the single battery voltage above (e.g. 12V batteries build a 12/24/48V bank).

ℹ️How many battery strings you have (or plan to have) wired in parallel.

%

ℹ️Typically 80-90% — check your inverter/UPS's datasheet.

%

ℹ️A design safety margin so the system still performs adequately as the battery ages — not a claim about a battery's current condition.

Cost

Enable Cost Estimation?

Estimated Backup Runtime: 4.55 hours

From 200 Ah (2 × 100Ah battery/ies) at 215 W load

Load Breakdown

EquipmentWattsQty
LED Bulb10 W× 5
Ceiling Fan75 W× 2
Router / Modem15 W× 1
Total Load215 W

Battery Bank

Battery type: Sealed Lead-Acid / AGM / Gel (VRLA) (depth of discharge: 60%)

System voltage: 12V1 × 12V in series

Parallel strings: 2 × 100Ah = 200 Ah total

Total batteries needed: 2 (1 series × 2 parallel)

Efficiency: 85%, aging/end-of-life margin: 80%

Informational Inverter/UPS Sizing

Suggested inverter/UPS rating: 600 VA (assumes 0.8 power factor, 25% headroom)

Assumptions Used

Assumes a sustained/continuous load — motor-driven appliances (like a refrigerator's compressor) cycle on and off, so actual runtime for such loads can vary from this estimate. This is a reference estimate — confirm with a licensed electrician for a permanent installation.

Need longer, whole-house backup instead of a battery bank? Generator Size Calculator →

Sizing your dwelling's full electrical service? Panel Size Calculator →

UPS Battery Backup VisualizationBattery Bank2 × 100AhLoad215 WBackup Runtime4.55 hrsDiagram simplified for clarity (not to scale)

What Is a UPS / Inverter Battery Capacity Calculator?

A UPS/inverter battery capacity calculator answers two related questions: given a battery bank, how long will it back up your equipment (Runtime mode); or given a target backup duration, what battery bank do you need to buy (Sizing mode). Both use the same underlying formula, accounting for battery chemistry's recommended depth of discharge, an aging/end-of-life safety margin, and inverter conversion efficiency.

This is a different calculation from the Generator Size Calculator (which sizes a fuel-powered generator's wattage, including motor starting surge) — use this tool for battery-based backup power, where sustained runtime from stored energy is what matters, not a brief startup transient.

Why getting battery capacity right matters:

  • An undersized battery bank runs out well before your outage ends, right when you need it most
  • An oversized bank costs significantly more than necessary for the same backup duration
  • Depth of discharge is the single most commonly overlooked factor — using a battery's full rated Ah instead of its safe usable capacity badly overstates runtime
  • Battery chemistry (lead-acid vs. lithium-ion) changes both the usable capacity and the cost per usable Ah substantially

UPS Battery Formula: How Is Capacity Calculated?

The core formula is the same in both directions — only which variable you're solving for changes.

Step 1 — Total Load

Total Load (W) = Sum of every equipment row's Watts × Quantity

This is the total connected load you want backed up, treated as a sustained/continuous draw.

Step 2 — Usable Energy

Usable Energy (Wh) = Battery Ah × System Voltage × Depth of Discharge × Aging Factor × Efficiency

Depth of discharge, an aging/end-of-life margin, and inverter conversion efficiency all reduce how much of the battery's rated capacity actually reaches your equipment.

Step 3a — Runtime Mode

Runtime (hours) = Usable Energy ÷ Total Load

Given a battery bank's Ah and voltage, solve directly for how long it backs up your load.

Step 3b — Sizing Mode

Required Ah = (Total Load × Target Runtime) ÷ (System Voltage × Depth of Discharge × Aging Factor × Efficiency)

Batteries Needed = Series Count (for voltage) × Parallel Count (rounded up, for capacity)

Given a target runtime, solve backward for the required battery capacity, then round up to a whole number of batteries.

Worked Example

This example walks through your current inputs above, using the same steps as the Formula section.

Input Values Used

InputValueWhy it is used
Equipment3 items, 215 W totalSets total load
BatterySealed Lead-Acid / AGM / Gel (VRLA), 60% DoDSets usable energy per Ah
ModeRuntime (given battery)Sets which variable is solved for

Steps 1-2 — Load and Usable Energy

CalculationResult
Total load215 W
Total battery capacity200 Ah
Usable energy979 Wh

Therefore, 200 Ah at 12V backs up 215 W of load for 4.55 hours.

Essential Checklist+

Complete these critical checks before approving the work or proceeding to the next construction stage.

11 Inspection Points
4 Verification Categories
Load Input Accuracy+
  • Actual nameplate/rated watts used for major equipment, not guessed from a generic chart
  • All equipment you actually intend to keep running is included, including easy-to-forget items
Battery Configuration & Depth of Discharge+
  • Battery chemistry selection matches the actual battery type purchased or planned
  • Planned usage confirmed not to regularly discharge the battery beyond its recommended DoD
  • Series/parallel wiring configuration confirmed against the actual battery's voltage rating
  • System voltage confirmed against the inverter/UPS's actual DC input requirement
Runtime / Sizing Calculation+
  • Correct calculation mode selected for the actual planning question being asked
Installation & Safety+
  • Battery placement and ventilation confirmed per the manufacturer's guidance
  • DC-side wiring and cable gauge sized for the actual current draw, not just the AC-side circuit
  • Overcurrent protection (fuse or breaker) confirmed on the battery bank, sized for the DC circuit
  • Permanent or whole-panel backup installation reviewed by a licensed electrician
Full QC Checklist+

Verification checklist for UPS/inverter battery capacity sizing — covering load input accuracy, battery configuration and depth of discharge, runtime/sizing calculation, and installation/safety. Use the Essential Checklist for critical checks before purchasing; expand to Full QC Checklist for complete verification.

21 Inspection Points
4 Verification Categories
Load Input Accuracy+
  • Actual nameplate/rated watts used for major equipment, not guessed from a generic chart
  • All equipment you actually intend to keep running is included, including easy-to-forget items
  • Motor-driven, cycling loads (refrigerator, sump pump) flagged as producing a variable, not perfectly steady, draw
  • Quantity field used correctly for repeated items, not double-counted as separate identical rows
  • Non-essential loads excluded, rather than listing everything in the house "just in case"
Battery Configuration & Depth of Discharge+
  • Battery chemistry selection matches the actual battery type purchased or planned
  • Planned usage confirmed not to regularly discharge the battery beyond its recommended DoD
  • Series/parallel wiring configuration confirmed against the actual battery's voltage rating
  • System voltage confirmed against the inverter/UPS's actual DC input requirement
  • Aging/end-of-life margin considered appropriate for the expected battery lifespan and how it will be used
Runtime / Sizing Calculation+
  • Correct calculation mode selected for the actual planning question being asked
  • Efficiency percentage reflects the actual inverter/UPS's rated efficiency, not left at a generic default
  • In Sizing mode, the actual achieved runtime (not just the target you entered) confirmed adequate
  • Understood that motor-driven/cycling loads' real-world backup time can differ from this steady-load estimate
  • Runtime and Sizing mode results cross-checked against each other where practical
Installation & Safety+
  • Battery placement and ventilation confirmed per the manufacturer's guidance
  • DC-side wiring and cable gauge sized for the actual current draw, not just the AC-side circuit
  • Overcurrent protection (fuse or breaker) confirmed on the battery bank, sized for the DC circuit
  • Inverter/UPS VA rating cross-checked against the actual connected load, not assumed automatically adequate
  • Permanent or whole-panel backup installation reviewed by a licensed electrician
  • Battery disposal/recycling plan confirmed per local regulations at end of life

Battery Chemistry Depth-of-Discharge Reference

Recommended maximum depth of discharge by battery chemistry — used as this calculator's default, overridable if your manufacturer specifies something different.

Battery ChemistryRecommended DoDNotes
Flooded Lead-Acid50%Lowest usable capacity per Ah; needs ventilation
Sealed Lead-Acid / AGM / Gel (VRLA)60%Maintenance-free, common for UPS/inverter use
Lithium-Ion (LiFePO4)85%Highest usable capacity per Ah; typically higher upfront cost

When should you use this UPS battery calculator?

  • Finding how long an existing or planned battery bank will back up your equipment.
  • Sizing a new battery bank for a target backup duration.
  • Comparing how battery chemistry (lead-acid vs. lithium-ion) changes the required battery count.
  • Planning backup power for a home office, refrigerator, or critical equipment during outages.
  • Estimating battery bank cost alongside the technical sizing.

Quick UPS Battery Sizing Tips

  • Never assume a battery's full rated Ah is usable — always apply the correct depth of discharge for its chemistry.
  • Use actual nameplate watts for major equipment instead of relying on generic presets.
  • Confirm your system voltage matches your inverter/UPS's actual DC input requirement before buying batteries.
  • Consider lithium-ion for a smaller, lighter battery bank at the same usable capacity, if budget allows.
  • Size with a realistic aging margin if you don't plan to replace batteries proactively as they age.

Common Mistakes

  • Sizing off a battery's full rated Ah instead of its safe usable capacity after depth of discharge.
  • Ignoring inverter/UPS conversion efficiency, overstating actual runtime by 10-20%.
  • Mixing up series (for voltage) and parallel (for capacity) wiring when planning a multi-battery bank.
  • Regularly discharging a battery well beyond its recommended DoD, significantly shortening its lifespan.
  • Assuming a plug-in UPS/inverter needs no transfer switch consideration when hard-wired into household circuits.

Limitations

  • Treats equipment load as steady/continuous — motor-driven, cycling loads (like a refrigerator) have a variable real-world draw this calculator approximates as constant.
  • Does not model battery starting/inrush current for motor-driven loads — for that, and for engine-driven generator sizing, use the Generator Size Calculator.
  • Does not model Peukert's effect (capacity loss at high discharge rates) or ambient temperature derating — both real factors for detailed engineering-grade sizing.
  • Practical parallel battery count is capped for a reasonable single bank — very large installations need an engineered design.
  • This is a planning reference estimate, not a substitute for a licensed electrician's review, especially for a permanent installation.

Disclaimer: This calculator provides approximate results for planning and estimation purposes only. Actual requirements may vary based on site conditions, materials, workmanship, and local building regulations. Always consult a qualified engineer, architect, or construction professional before making final decisions.

FAQ

Backup Time (hours) = Usable Energy (Wh) ÷ Total Load (W), where Usable Energy = Battery Capacity (Ah) × System Voltage (V) × Depth of Discharge × Aging Factor × Inverter Efficiency. List your equipment's watts (with a quantity for repeated items), enter your battery's Ah rating and voltage, and the calculator applies this formula automatically.
"Runtime" mode answers: I already have (or am evaluating) a specific battery — how long will it run my load? "Sizing" mode answers the reverse: I have a target backup duration — what battery bank (Ah, and how many batteries) do I need to buy? Use whichever matches the actual question you're trying to answer.