TryBuildCalc

PCC Thickness Calculator PCC quantity by thickness estimator

Calculate PCC cement, sand, and aggregate instantly.

PCC Dimensions

ℹ️Typical: 75-100 mm (foundation blinding), 100-125 mm (flooring / floor base)

Common PCC thickness:

Cost

Enable Cost Estimation?

For a 12.00 footprint, you need approximately 1.89 (66.7 cft) of PCC concrete — 8.4 cement bags.

PCC Concrete

Wet volume (before wastage): 1.800

Dry volume: 2.772

Final quantity (with wastage): 1.89 (66.7 cft)

Materials

Cement: 8.4 bags (420 kg)

Sand: 0.87 (30.8 cft)

Aggregate: 1.75 (61.7 cft)

Assumptions Used

Dry volume factor: 1.54 | Cement bag: 50 kg / 0.0347 m³ | PCC is non-reinforced — no steel, and no shuttering (cast directly against the excavation or a prepared subgrade, not panel formwork).

PCC Layer (Plan & Cross-Section)Plan ViewPCC FootprintLength: 4 mWidth: 3 mCross-SectionFooting / SlabPCC LayerSoil / GroundThickness: 150 mmDiagram simplified for clarity (not to scale). Footing/slab above the PCC is illustrative context only.

Looking for the verification checklist, reference tables, tips, or common mistakes?See the complete PCC Calculator.

PCC quantity by thickness

This page is pre-filled with a 150 mm thickness — a common figure for PCC hard standing or a heavier-duty base layer — so you can see how thickness drives concrete volume for your footprint.

PCC thickness has no single fixed answer: it depends on the application (blinding vs. hard standing vs. floor base) and the load it needs to support. Edit the thickness above to compare quantities against different design options.

  • Blinding layers: commonly 75-100 mm.
  • Floor base / levelling courses: commonly 100-125 mm.
  • Hard standing and pathways subject to vehicle loads: commonly 125-150 mm+.

How Is PCC Quantity Calculated?

PCC quantity is calculated from wet concrete volume, a dry-volume correction factor, and cement-sand-aggregate mix ratio distribution, then an optional cost estimate on top.

Step 1 — PCC Volume

Wet Volume = Length × Width × Thickness

Dry Volume = Wet Volume × 1.54

Dry volume accounts for the voids between aggregate particles that disappear once the concrete is mixed and compacted. The dry volume is split into cement, sand, and aggregate using the selected mix ratio, and wastage is applied once to the final quantities.

Step 2 — Cement Bags

Cement Volume = Dry Volume × (Cement Ratio Part ÷ Total Ratio Parts)

Cement Bags = Cement Volume ÷ 0.0347 m³/bag (50 kg bags)

Sand and aggregate are split the same way, using their own ratio parts. One standard cement bag (50 kg) occupies approximately 0.0347 m³.

Step 3 — Final Quantity with Wastage

Final Wet Volume = Wet Volume × (1 + Wastage %)

This final wet volume (and the wastage-adjusted cement/sand/aggregate figures) is the practical quantity to order or batch on site — shown separately from the theoretical pre-wastage volume.

Worked Example

This example walks through your current inputs above, using the same steps as the Formula section.

Input Values Used

InputValueWhy it is used
Length × width × thickness4m × 3m × 150mmSets the wet concrete volume
Mix ratio / wastage1:3:6, 5% wastageSplits dry volume into cement/sand/aggregate and adds a buffer for site losses

Step 1 — Volume

CalculationSubstitutionResult
Wet volume4m × 3m × 150mm1.800
Dry volume1.800 × 1.542.772
With 5% wastage1.800 × 1.051.890 m³ (66.7 cft)

Step 2 — Materials

MaterialQuantity
Cement8.4 bags (420 kg)
Sand0.87 m³ (30.8 cft)
Aggregate1.75 m³ (61.7 cft)

Therefore, approximately 1.89 (66.7 cft) of PCC concrete should be ordered or batched for this layer, needing 8.4 cement bags, while sand and aggregate are estimated separately for site mixing.

Disclaimer: This calculator provides approximate results for planning and estimation purposes only. Actual requirements may vary based on site conditions, materials, workmanship, and local building regulations. Always consult a qualified engineer, architect, or construction professional before making final decisions.

FAQ

It depends on the application — blinding layers are typically thinner (75-100 mm) than hard standing subject to vehicle loads (125-150 mm+). Confirm against your project's structural drawing for anything beyond routine residential work.
Not automatically — thickness and mix ratio are set independently based on the application. A thicker hard-standing layer commonly pairs with a stronger mix (1:2:4), but confirm both together against your project's requirements.