TryBuildCalc

PCC for Footing Calculator Footing blinding layer estimator

Calculate PCC cement, sand, and aggregate instantly.

PCC Dimensions

ℹ️Typical: 75-100 mm (foundation blinding), 100-125 mm (flooring / floor base)

Common PCC thickness:

Cost

Enable Cost Estimation?

For a 12.00 footprint, you need approximately 0.95 (33.4 cft) of PCC concrete — 4.2 cement bags.

PCC Concrete

Wet volume (before wastage): 0.900

Dry volume: 1.386

Final quantity (with wastage): 0.95 (33.4 cft)

Materials

Cement: 4.2 bags (210 kg)

Sand: 0.44 (15.4 cft)

Aggregate: 0.87 (30.8 cft)

Assumptions Used

Dry volume factor: 1.54 | Cement bag: 50 kg / 0.0347 m³ | PCC is non-reinforced — no steel, and no shuttering (cast directly against the excavation or a prepared subgrade, not panel formwork).

PCC Layer (Plan & Cross-Section)Plan ViewPCC FootprintLength: 4 mWidth: 3 mCross-SectionFooting / SlabPCC LayerSoil / GroundThickness: 75 mmDiagram simplified for clarity (not to scale). Footing/slab above the PCC is illustrative context only.

Looking for the verification checklist, reference tables, tips, or common mistakes?See the complete PCC Calculator.

PCC blinding layer for a footing

This page is pre-filled with a 75 mm thickness — typical for a PCC blinding layer cast below a footing before reinforcement is fixed.

Remember to size the PCC footprint larger than the footing's own plan dimensions — extending roughly 75 mm beyond the footing edge on each side gives working space for formwork and reinforcement fixing.

  • Footing blinding is typically 75-100 mm thick, using a lean mix such as 1:3:6.
  • PCC footprint should extend beyond the footing's plan edges, not match them exactly.
  • Use the Concrete Footing Calculator to size the footing itself.

How Is PCC Quantity Calculated?

PCC quantity is calculated from wet concrete volume, a dry-volume correction factor, and cement-sand-aggregate mix ratio distribution, then an optional cost estimate on top.

Step 1 — PCC Volume

Wet Volume = Length × Width × Thickness

Dry Volume = Wet Volume × 1.54

Dry volume accounts for the voids between aggregate particles that disappear once the concrete is mixed and compacted. The dry volume is split into cement, sand, and aggregate using the selected mix ratio, and wastage is applied once to the final quantities.

Step 2 — Cement Bags

Cement Volume = Dry Volume × (Cement Ratio Part ÷ Total Ratio Parts)

Cement Bags = Cement Volume ÷ 0.0347 m³/bag (50 kg bags)

Sand and aggregate are split the same way, using their own ratio parts. One standard cement bag (50 kg) occupies approximately 0.0347 m³.

Step 3 — Final Quantity with Wastage

Final Wet Volume = Wet Volume × (1 + Wastage %)

This final wet volume (and the wastage-adjusted cement/sand/aggregate figures) is the practical quantity to order or batch on site — shown separately from the theoretical pre-wastage volume.

Worked Example

This example walks through your current inputs above, using the same steps as the Formula section.

Input Values Used

InputValueWhy it is used
Length × width × thickness4m × 3m × 75mmSets the wet concrete volume
Mix ratio / wastage1:3:6, 5% wastageSplits dry volume into cement/sand/aggregate and adds a buffer for site losses

Step 1 — Volume

CalculationSubstitutionResult
Wet volume4m × 3m × 75mm0.900
Dry volume0.900 × 1.541.386
With 5% wastage0.900 × 1.050.945 m³ (33.4 cft)

Step 2 — Materials

MaterialQuantity
Cement4.2 bags (210 kg)
Sand0.44 m³ (15.4 cft)
Aggregate0.87 m³ (30.8 cft)

Therefore, approximately 0.95 (33.4 cft) of PCC concrete should be ordered or batched for this layer, needing 4.2 cement bags, while sand and aggregate are estimated separately for site mixing.

Disclaimer: This calculator provides approximate results for planning and estimation purposes only. Actual requirements may vary based on site conditions, materials, workmanship, and local building regulations. Always consult a qualified engineer, architect, or construction professional before making final decisions.

FAQ

Extend the PCC footprint roughly 75 mm beyond the footing's plan edge on each side, giving working space for formwork and reinforcement fixing without disturbing the blinding edge.
1:3:6 (a lean PCC mix) is commonly used for footing blinding, since it's a non-structural layer whose main job is providing a clean, level working surface.