Blinding Concrete Calculator PCC blinding layer estimator

Calculate PCC cement, sand, and aggregate instantly.

PCC Dimensions

ℹ️Typical: 75-100 mm (foundation blinding), 100-125 mm (flooring / floor base)

Common PCC thickness:

Cost

Enable Cost Estimation?

For a 12.00 footprint, you need approximately 0.95 (33.4 cft) of PCC concrete — 4.2 cement bags.

PCC Concrete

Wet volume (before wastage): 0.900

Dry volume: 1.386

Final quantity (with wastage): 0.95 (33.4 cft)

Materials

Cement: 4.2 bags (210 kg)

Sand: 0.44 (15.4 cft)

Aggregate: 0.87 (30.8 cft)

Assumptions Used

Dry volume factor: 1.54 | Cement bag: 50 kg / 0.0347 m³ | PCC is non-reinforced — no steel, and no shuttering (cast directly against the excavation or a prepared subgrade, not panel formwork).

PCC Layer (Plan & Cross-Section)Plan ViewPCC FootprintLength: 4 mWidth: 3 mCross-SectionFooting / SlabPCC LayerSoil / GroundThickness: 75 mmDiagram simplified for clarity (not to scale). Footing/slab above the PCC is illustrative context only.

Looking for the verification checklist, reference tables, tips, or common mistakes?See the complete PCC Calculator.

Blinding concrete quantity estimate

"Blinding concrete" and "PCC" are commonly used interchangeably in foundation work — a thin, non-structural layer that seals the excavation base and provides a clean, level surface for reinforcement fixing. This page is pre-filled with a typical 75 mm blinding thickness and 1:3:6 mix.

Edit the dimensions above and the quantity breakdown and worked example update from the active values.

  • Blinding is placed directly onto the prepared excavation base, sealing it against groundwater and loose soil.
  • Typical thickness: 50-100 mm, using a lean-to-standard mix (1:4:8 or 1:3:6).
  • Extend blinding beyond the footing's plan edge for working space, not flush with it.

How Is PCC Quantity Calculated?

PCC quantity is calculated from wet concrete volume, a dry-volume correction factor, and cement-sand-aggregate mix ratio distribution, then an optional cost estimate on top.

Step 1 — PCC Volume

Wet Volume = Length × Width × Thickness

Dry Volume = Wet Volume × 1.54

Dry volume accounts for the voids between aggregate particles that disappear once the concrete is mixed and compacted. The dry volume is split into cement, sand, and aggregate using the selected mix ratio, and wastage is applied once to the final quantities.

Step 2 — Cement Bags

Cement Volume = Dry Volume × (Cement Ratio Part ÷ Total Ratio Parts)

Cement Bags = Cement Volume ÷ 0.0347 m³/bag (50 kg bags)

Sand and aggregate are split the same way, using their own ratio parts. One standard cement bag (50 kg) occupies approximately 0.0347 m³.

Step 3 — Final Quantity with Wastage

Final Wet Volume = Wet Volume × (1 + Wastage %)

This final wet volume (and the wastage-adjusted cement/sand/aggregate figures) is the practical quantity to order or batch on site — shown separately from the theoretical pre-wastage volume.

Worked Example

This example walks through your current inputs above, using the same steps as the Formula section.

Input Values Used

InputValueWhy it is used
Length × width × thickness4m × 3m × 75mmSets the wet concrete volume
Mix ratio / wastage1:3:6, 5% wastageSplits dry volume into cement/sand/aggregate and adds a buffer for site losses

Step 1 — Volume

CalculationSubstitutionResult
Wet volume4m × 3m × 75mm0.900
Dry volume0.900 × 1.541.386
With 5% wastage0.900 × 1.050.945 m³ (33.4 cft)

Step 2 — Materials

MaterialQuantity
Cement4.2 bags (210 kg)
Sand0.44 m³ (15.4 cft)
Aggregate0.87 m³ (30.8 cft)

Therefore, approximately 0.95 (33.4 cft) of PCC concrete should be ordered or batched for this layer, needing 4.2 cement bags, while sand and aggregate are estimated separately for site mixing.

Disclaimer: This calculator provides approximate results for planning and estimation purposes only. Actual requirements may vary based on site conditions, materials, workmanship, and local building regulations. Always consult a qualified engineer, architect, or construction professional before making final decisions.

FAQ

Yes — "blinding concrete" and "PCC" (Plain Cement Concrete) describe the same non-reinforced layer used to prepare a clean, level, and sealed base before reinforced concrete or masonry work begins.
Blinding seals the excavation base against groundwater and loose soil, provides a clean surface for setting out and fixing reinforcement, and prevents reinforcement bar chairs from sinking into soft ground.