Trench Excavation Verification Checklist
π Last updated: June 22, 2026
Essential Checklist+β
Complete these critical checks before approving the work or proceeding to the next construction stage.
β18 Inspection Points
β4 Verification Categories
βDimensions and Route+-
- Trench length was measured along the actual route on site β not scaled from a drawing.
- Trench width is the excavation width β not the pipe or footing width. Add at least 300mm each side for installation working space.
- Trench depth is measured from existing ground level to the bottom of the pipe bedding or foundation β including any granular bedding layer.
- Changes in trench depth along the route (due to gradient or crossing services) were accounted for by splitting the trench into sections.
- Dimensions were entered in consistent units.
- The trench route was walked on site and crossed services marked before dimensions were finalised.
βServices and Underground Hazards+-
- All existing underground services along the trench route were identified from utility drawings and marked on the ground.
- Trial holes were dug by hand within 500mm of any marked service before mechanical excavation began.
- Electrical supply to cables within the trench zone was isolated or the cable route was confirmed safe before digging.
- Minimum clearance from existing services was maintained β 150mm from water pipes, 300mm from gas pipes, 500mm from HV cables.
βShoring and Safety+-
- Trenches deeper than 1.2m in loose, sandy, or water-bearing soil have shoring, trench boxes, or battered sides.
- Side battering (slope) for unshored trenches in non-cohesive soil is at least 1:1 from the trench bottom edge.
- Excavated spoil is placed at least 1.0m from the trench edge β nearer placement increases collapse risk.
- Safe means of entry and exit (ladder or steps) are provided at intervals not exceeding 6m for trenches over 1.2m deep.
- Open trenches across pedestrian or vehicle routes are covered with rated trench plates when not being worked.
βVolume, Bedding, and Reinstatement+-
- A bulking factor of 20β30% was applied to the calculated trench volume for spoil haulage.
- Pipe bedding volume (granular material below and around the pipe) was calculated separately and added to the order.
- Imported granular backfill specification was confirmed β clean gravel or crusher dust, not site-won clay or organic soil.
Full QC Checklist+β
Verify trench dimensions, utilities, support, bedding, disposal, and safety.
β23 Inspection Points
β4 Verification Categories
βDimensions and Route+-
- Trench length was measured along the actual route on site β not scaled from a drawing.
- Trench width is the excavation width β not the pipe or footing width. Add at least 300mm each side for installation working space.
- Trench depth is measured from existing ground level to the bottom of the pipe bedding or foundation β including any granular bedding layer.
- Changes in trench depth along the route (due to gradient or crossing services) were accounted for by splitting the trench into sections.
- Dimensions were entered in consistent units.
- The trench route was walked on site and crossed services marked before dimensions were finalised.
βServices and Underground Hazards+-
- All existing underground services along the trench route were identified from utility drawings and marked on the ground.
- Trial holes were dug by hand within 500mm of any marked service before mechanical excavation began.
- Electrical supply to cables within the trench zone was isolated or the cable route was confirmed safe before digging.
- Gas, water, and telecom authorities were notified before trenching in public or shared access areas.
- Minimum clearance from existing services was maintained β 150mm from water pipes, 300mm from gas pipes, 500mm from HV cables.
βShoring and Safety+-
- Trenches deeper than 1.2m in loose, sandy, or water-bearing soil have shoring, trench boxes, or battered sides.
- Side battering (slope) for unshored trenches in non-cohesive soil is at least 1:1 from the trench bottom edge.
- Excavated spoil is placed at least 1.0m from the trench edge β nearer placement increases collapse risk.
- Safe means of entry and exit (ladder or steps) are provided at intervals not exceeding 6m for trenches over 1.2m deep.
- Trench is inspected by a competent person at the start of each shift and after rain or vibration from nearby plant.
- Open trenches across pedestrian or vehicle routes are covered with rated trench plates when not being worked.
βVolume, Bedding, and Reinstatement+-
- A bulking factor of 20β30% was applied to the calculated trench volume for spoil haulage.
- Pipe bedding volume (granular material below and around the pipe) was calculated separately and added to the order.
- Reinstatement material volume was calculated as: trench volume β pipe volume β bedding volume.
- Imported granular backfill specification was confirmed β clean gravel or crusher dust, not site-won clay or organic soil.
- Reinstatement compaction requirements (layers, passes, equipment) were confirmed with the engineer or road authority.
- Surface reinstatement (tarmac, paving, concrete) was specified and costed separately from the earthwork.
Inspection Notes+-
Use the latest approved drawings, specifications, and site measurements.
Complete all critical checks before proceeding to the next work stage.
Record deviations and confirm rectification where required.
Inspection Notes
Use the latest approved drawings, specifications, and site measurements.
Complete all critical checks before proceeding to the next work stage.
Record deviations and confirm rectification where required.