Complete these critical checks before approving the work or proceeding to the next construction stage.

βœ“17 Inspection Points
βœ“5 Verification Categories
βœ“Measurement and Input+
  • Dimensions were physically measured on site with a tape β€” not taken from sale documents or property cards.
  • All four boundary lengths were measured independently β€” opposite sides of a plot are rarely equal.
  • For irregular plots, either the polygon (custom points) mode was used with real boundary measurements, or the plot was divided into triangles/rectangles and each section measured separately β€” not eyeballed as one averaged shape.
  • Dimensions were entered in the correct unit β€” do not mix metres and feet in the same calculation.
  • For quadrilateral plots, the angle or diagonal entered matches the site geometry β€” not an assumed 90Β°.
  • For circular plots, the radius/diameter toggle matches what was actually measured on site β€” entering a measured diameter into the radius field (or vice versa) quadruples or quarters the resulting area.
  • For triangular and trapezoid plots, the perpendicular (vertical) height was entered β€” not the sloping side length, which overstates the area if used directly.
βœ“Irregular Plot (Polygon) Verification+
  • Every boundary corner was recorded, walked in one consistent direction around the plot β€” mixing clockwise and counter-clockwise entries for different corners produces an incorrect area.
  • All corner offsets (X, Y) were measured from the same fixed reference point and baseline direction β€” switching reference points partway through introduces cumulative error.
  • The number of corner points entered matches the actual number of direction changes on the boundary β€” a missed corner silently cuts off part of the plot.
βœ“Unit Conversion+
  • The output unit matches what is required for the task at hand β€” sq ft, mΒ², sq yd, acres, or hectares as applicable.
  • If using a local/regional land unit (such as cent, guntha, ankanam, marla, or kanal), the exact regional definition is confirmed first β€” these units vary by country and even by state/province, not just by name.
βœ“Legal and Site Verification+
  • The calculated area was compared against the area stated in the title deed, land registry extract, or official survey record β€” discrepancies must be resolved before construction.
  • Setback and road-widening reservations were identified β€” these reduce the usable plot area below the total area.
βœ“Deductions, Cost & Value Verification+
  • Road widening, setback, and corner-chamfer deductions were measured on site or taken from an approved layout plan β€” not guessed as a round percentage of the gross area.
  • The deduction unit (sq ft, sq yd, or mΒ²) matches the unit the gross area is being reasoned about in β€” mixing units here silently under- or over-states the net usable area.
  • The rate unit (per sq ft, sq yd, mΒ², acre, or hectare) matches how the rate was actually quoted β€” applying a per-acre rate as if it were per-sq-ft (or vice versa) produces a wildly wrong estimated value.
Full QC Checklist+

Verify plot measurements, units, boundaries, and legal area assumptions.

βœ“27 Inspection Points
βœ“5 Verification Categories
βœ“Measurement and Input+
  • Dimensions were physically measured on site with a tape β€” not taken from sale documents or property cards.
  • All four boundary lengths were measured independently β€” opposite sides of a plot are rarely equal.
  • For irregular plots, either the polygon (custom points) mode was used with real boundary measurements, or the plot was divided into triangles/rectangles and each section measured separately β€” not eyeballed as one averaged shape.
  • Diagonal measurements were taken to verify right angles on rectangular plots.
  • Dimensions were entered in the correct unit β€” do not mix metres and feet in the same calculation.
  • For quadrilateral plots, the angle or diagonal entered matches the site geometry β€” not an assumed 90Β°.
  • For circular plots, the radius/diameter toggle matches what was actually measured on site β€” entering a measured diameter into the radius field (or vice versa) quadruples or quarters the resulting area.
  • For triangular and trapezoid plots, the perpendicular (vertical) height was entered β€” not the sloping side length, which overstates the area if used directly.
βœ“Irregular Plot (Polygon) Verification+
  • Every boundary corner was recorded, walked in one consistent direction around the plot β€” mixing clockwise and counter-clockwise entries for different corners produces an incorrect area.
  • All corner offsets (X, Y) were measured from the same fixed reference point and baseline direction β€” switching reference points partway through introduces cumulative error.
  • The number of corner points entered matches the actual number of direction changes on the boundary β€” a missed corner silently cuts off part of the plot.
  • For a large or complex boundary, the calculated area was sanity-checked against a rough estimate (e.g. bounding rectangle minus obvious cut corners) before relying on the exact figure.
βœ“Unit Conversion+
  • The output unit matches what is required for the task at hand β€” sq ft, mΒ², sq yd, acres, or hectares as applicable.
  • If using a local/regional land unit (such as cent, guntha, ankanam, marla, or kanal), the exact regional definition is confirmed first β€” these units vary by country and even by state/province, not just by name.
  • Any regional land unit conversion used is checked against a local authoritative source before being relied on for legal or high-value decisions, since this calculator's regional conversions are common reference values, not a universal legal standard.
  • For legal or sale purposes, area was cross-checked against the registered deed, land registry extract, or official survey record.
βœ“Legal and Site Verification+
  • The calculated area was compared against the area stated in the title deed, land registry extract, or official survey record β€” discrepancies must be resolved before construction.
  • Setback and road-widening reservations were identified β€” these reduce the usable plot area below the total area.
  • The corner markers or boundary stones are clearly visible and undisturbed on site.
  • For large or disputed plots, a licensed surveyor's measurement supersedes tape-measure calculations.
  • Floor Area Ratio (FAR/FSI) and ground coverage calculations use the net plot area after deducting road reservations, not the gross plot area.
  • Municipal or local authority approval drawings show dimensions that may differ from the actual site β€” always verify on ground.
βœ“Deductions, Cost & Value Verification+
  • Road widening, setback, and corner-chamfer deductions were measured on site or taken from an approved layout plan β€” not guessed as a round percentage of the gross area.
  • The deduction unit (sq ft, sq yd, or mΒ²) matches the unit the gross area is being reasoned about in β€” mixing units here silently under- or over-states the net usable area.
  • The land rate entered reflects the current market rate for this specific location and plot category (corner plot, road-facing, interior) β€” a generic area-average rate can be significantly off for a specific plot.
  • The rate unit (per sq ft, sq yd, mΒ², acre, or hectare) matches how the rate was actually quoted β€” applying a per-acre rate as if it were per-sq-ft (or vice versa) produces a wildly wrong estimated value.
  • The estimated plot value is treated as an indicative planning figure only, and cross-checked against an actual valuation, registration/circle rate, or broker quote before any transactional decision.
Inspection Notes+
Use the latest approved drawings, specifications, and site measurements.
Complete all critical checks before proceeding to the next work stage.
Record deviations and confirm rectification where required.

Related Calculators & Guides

FAQ

Use it after collecting the project inputs and again before approving or closing the relevant work stage.
No. It supports verification but does not replace approved drawings, specifications, codes, manufacturer requirements, or professional inspection.