Warehouse Lighting Load Calculator (0.25 VA/ft² — With Feeder Demand Factor)
Calculate your warehouse lighting load.
🕒 Last updated: August 29, 2026
Inputs
ℹ️Sets the NEC Table 220.42 unit lighting load (VA/ft²) and whether a demand factor reduction applies.
ℹ️Measured from outside building dimensions per NEC 220.12/220.42, not usable/carpet area.
Show Window Lighting
Track Lighting
Circuit Sizing
Cost
Branch Circuits Needed: 5 × 20A @ 277V
For 100,000 ft² of Warehouse (Storage) — branch circuit design load 25,000 VA
General Lighting Load
Unit load: 0.25 VA/ft²
Connected load: 25,000 VA
Already includes the 125% continuous-load margin, per NEC Table 220.42(A)'s own note.
Branch Circuit Sizing
Circuit design load: 25,000 VA
Capacity per circuit: 5,540 VA (20A × 277V, full rating)
Uses the connected load, not the demand-reduced feeder load below — branch circuits don't get diversity with each other.
Feeder / Service Demand Load (Informational)
After Table 220.45 demand factor: 18,750 VA
Total feeder/service demand: 18,750 VA (67.7 A)
This is the load a feeder/service supplying this space would need to carry — not the same figure as the branch circuit design load above, and not used for the circuit count.
Assumptions Used
NEC 2023 220.12/Table 220.42(A) (general lighting unit loads — default method, not the optional 220.42(B) energy-code alternate), Table 220.45 (feeder/service demand factors), 220.46(A)/(B) (show window/track lighting). Branch circuit count uses the connected (non-demand-factor-reduced) load, since demand factors apply to feeder/service sizing only. Single-phase VA/voltage estimate — a genuine 3-phase panel schedule needs per-phase balancing beyond this calculator's scope. This is a reference estimate — confirm with a licensed electrician before installation.
Checking your panel has enough total capacity for this plus everything else? Panel Size Calculator →
Need to size the wire and breaker for one of these circuits? Wire Size Calculator →
Looking for the verification checklist, reference tables, tips, or common mistakes?See the complete Lighting Load Calculator.
Storage warehouse lighting load sizing
Storage warehouses have the lowest common unit lighting load — just 0.25 VA/ft² under NEC Table 220.42(A) — but also receive a Table 220.45 demand factor reduction on the portion of the load above 12,500 VA, for feeder/service sizing.
This page is pre-set to a 100,000 sq ft warehouse, where the demand factor meaningfully reduces the feeder/service figure — but not the branch circuit count, which always uses the connected (undiminished) load.
- 100,000 ft² × 0.25 VA/ft² = 25,000 VA connected load.
- Feeder demand factor: first 12,500 VA at 100%, remainder at 50% — 12,500 + (12,500 × 0.5) = 18,750 VA feeder demand (informational only).
- Branch circuit count uses the full 25,000 VA connected load: at 277V on 20A circuits (5,540 VA capacity each), this needs 5 branch circuits.
Lighting Load Formula: How Is It Calculated?
This calculator computes two different totals: a feeder/service demand load (informational) and a branch circuit design load (what actually sets the circuit count) — they are not the same figure, and using the wrong one under- or over-sizes the result.
Step 1 — Connected Lighting Load
Connected Load (VA) = Floor Area (ft²) × Unit Load (VA/ft²)
The unit load comes from NEC Table 220.42(A) (or 220.12 for dwelling units) based on your occupancy type. Per Table 220.42(A)'s own note, this figure already includes the NEC 210.20(A) 125% continuous-load multiplier — no additional factor is applied to it anywhere below.
Step 2 — Feeder/Service Demand Load (Informational Only)
Feeder Demand = (Connected Load × Table 220.45 demand factor) + Show Window Design VA + Track Lighting Design VA
(demand factor applies to dwelling, hospital, hotel/motel, and warehouse only — all others: 100%)
Only certain occupancies receive a demand factor reduction, applied in tiers to different VA brackets — this reduction reflects that not every circuit in a large building draws its full load at once, from the perspective of the feeder/service supplying all of them together.
Step 3 — Branch Circuit Design Load & Circuit Count
Circuit Design Load = Connected Load + Show Window Design VA + Track Lighting Design VA
Circuits Needed = ceil(Circuit Design Load ÷ (Breaker A × Voltage))
Circuit count uses the CONNECTED load, not the demand-reduced feeder figure — demand factors are a feeder/service tool only; individual branch circuits don't get diversity with each other and must each be sized for their own actual assigned load (NEC 210.19). Show window (200 VA/ft) and track lighting (150 VA per 2 ft) come from NEC 220.46, are never demand-factor-reduced, and — since no note exempts them the way Table 220.42(A) is exempted — get their own explicit ×1.25 continuous-load factor (their "Design VA") before being added in. Because both totals are already fully design-value-inclusive, circuit capacity uses the breaker's full rating with no further 80%/125% adjustment.
Worked Example
This example walks through your current inputs above, using the same steps as the Formula section.
Input Values Used
| Input | Value | Why it is used |
|---|---|---|
| Occupancy | Warehouse (Storage) (0.25 VA/ft²) | Sets the unit lighting load and demand factor category |
| Floor Area | 100,000 ft² | Multiplied by the unit load for connected VA |
| Circuit | 20A @ 277V | Sets each circuit's usable capacity |
Step 1 — Connected Load
| Calculation | 100,000 × 0.25 |
| Connected load (125% already included) | 25,000 VA |
Step 2 — Feeder/Service Demand Load (Informational)
| Demand factor category | warehouse |
| General lighting demand load | 18,750 VA |
| Total feeder/service demand (not used for circuit count) | 18,750 VA (67.7 A) |
Step 3 — Branch Circuit Design Load & Circuit Count
| Circuit design load (connected load, not demand-reduced) | 25,000 VA |
| Capacity per circuit | 20 × 277 = 5,540 VA |
| Circuits needed | ceil(25,000 ÷ 5,540) = 5 |
Therefore, for 100,000 ft² of Warehouse (Storage), you need 5 circuits at 20A / 277V.
Related Calculators
Disclaimer: This calculator provides approximate results for planning and estimation purposes only. Actual requirements may vary based on site conditions, materials, workmanship, and local building regulations. Always consult a qualified engineer, architect, or construction professional before making final decisions.