TryBuildCalc

Lighting Load Calculator (NEC 220.12/220.42 — General Lighting Load)

Calculate your lighting load instantly.

Inputs

ℹ️Sets the NEC Table 220.42 unit lighting load (VA/ft²) and whether a demand factor reduction applies.

ft²

ℹ️Measured from outside building dimensions per NEC 220.12/220.42, not usable/carpet area.

Show Window Lighting

Include Show Window?

Track Lighting

Include Track Lighting?

Circuit Sizing

Cost

Enable Cost Estimation?

Branch Circuits Needed: 2 × 20A @ 277V

For 5,000 ft² of Office / Bank — branch circuit design load 6,500 VA

General Lighting Load

Unit load: 1.30 VA/ft²

Connected load: 6,500 VA

Already includes the 125% continuous-load margin, per NEC Table 220.42(A)'s own note.

Branch Circuit Sizing

Circuit design load: 6,500 VA

Capacity per circuit: 5,540 VA (20A × 277V, full rating)

Uses the connected load, not the demand-reduced feeder load below — branch circuits don't get diversity with each other.

Feeder / Service Demand Load (Informational)

After Table 220.45 demand factor: 6,500 VA

Total feeder/service demand: 6,500 VA (23.5 A)

This is the load a feeder/service supplying this space would need to carry — not the same figure as the branch circuit design load above, and not used for the circuit count.

Assumptions Used

NEC 2023 220.12/Table 220.42(A) (general lighting unit loads — default method, not the optional 220.42(B) energy-code alternate), Table 220.45 (feeder/service demand factors), 220.46(A)/(B) (show window/track lighting). Branch circuit count uses the connected (non-demand-factor-reduced) load, since demand factors apply to feeder/service sizing only. Single-phase VA/voltage estimate — a genuine 3-phase panel schedule needs per-phase balancing beyond this calculator's scope. This is a reference estimate — confirm with a licensed electrician before installation.

Checking your panel has enough total capacity for this plus everything else? Panel Size Calculator →

Need to size the wire and breaker for one of these circuits? Wire Size Calculator →

Lighting Load SizingLit Area6,500 VA23.5 APanel2 circuitsDiagram simplified for clarity (not to scale)

Looking for the verification checklist, reference tables, tips, or common mistakes?See the complete Lighting Load Calculator.

General lighting load estimate

This page gives the full combined result — connected load, demand load, total current, and branch circuits needed — from one occupancy type and floor area.

It's the same calculator behind every other lighting variant on this site, just without a specific occupancy scenario pre-selected — useful for a general check before finalizing your actual building details.

  • Applies the correct NEC Table 220.42(A) unit load for your occupancy type automatically.
  • Applies NEC Table 220.45 demand factors only for feeder/service sizing, where the code actually allows a reduction — never for the branch circuit count.
  • Outputs a ready-to-use branch circuit count at your chosen voltage and breaker size.

Lighting Load Formula: How Is It Calculated?

This calculator computes two different totals: a feeder/service demand load (informational) and a branch circuit design load (what actually sets the circuit count) — they are not the same figure, and using the wrong one under- or over-sizes the result.

Step 1 — Connected Lighting Load

Connected Load (VA) = Floor Area (ft²) × Unit Load (VA/ft²)

The unit load comes from NEC Table 220.42(A) (or 220.12 for dwelling units) based on your occupancy type. Per Table 220.42(A)'s own note, this figure already includes the NEC 210.20(A) 125% continuous-load multiplier — no additional factor is applied to it anywhere below.

Step 2 — Feeder/Service Demand Load (Informational Only)

Feeder Demand = (Connected Load × Table 220.45 demand factor) + Show Window Design VA + Track Lighting Design VA

(demand factor applies to dwelling, hospital, hotel/motel, and warehouse only — all others: 100%)

Only certain occupancies receive a demand factor reduction, applied in tiers to different VA brackets — this reduction reflects that not every circuit in a large building draws its full load at once, from the perspective of the feeder/service supplying all of them together.

Step 3 — Branch Circuit Design Load & Circuit Count

Circuit Design Load = Connected Load + Show Window Design VA + Track Lighting Design VA

Circuits Needed = ceil(Circuit Design Load ÷ (Breaker A × Voltage))

Circuit count uses the CONNECTED load, not the demand-reduced feeder figure — demand factors are a feeder/service tool only; individual branch circuits don't get diversity with each other and must each be sized for their own actual assigned load (NEC 210.19). Show window (200 VA/ft) and track lighting (150 VA per 2 ft) come from NEC 220.46, are never demand-factor-reduced, and — since no note exempts them the way Table 220.42(A) is exempted — get their own explicit ×1.25 continuous-load factor (their "Design VA") before being added in. Because both totals are already fully design-value-inclusive, circuit capacity uses the breaker's full rating with no further 80%/125% adjustment.

Worked Example

This example walks through your current inputs above, using the same steps as the Formula section.

Input Values Used

InputValueWhy it is used
OccupancyOffice / Bank (1.30 VA/ft²)Sets the unit lighting load and demand factor category
Floor Area5,000 ft²Multiplied by the unit load for connected VA
Circuit20A @ 277VSets each circuit's usable capacity

Step 1 — Connected Load

Calculation5,000 × 1.30
Connected load (125% already included)6,500 VA

Step 2 — Feeder/Service Demand Load (Informational)

Demand factor categoryNone — 100% of connected load
General lighting demand load6,500 VA
Total feeder/service demand (not used for circuit count)6,500 VA (23.5 A)

Step 3 — Branch Circuit Design Load & Circuit Count

Circuit design load (connected load, not demand-reduced)6,500 VA
Capacity per circuit20 × 277 = 5,540 VA
Circuits neededceil(6,500 ÷ 5,540) = 2

Therefore, for 5,000 ft² of Office / Bank, you need 2 circuits at 20A / 277V.

Disclaimer: This calculator provides approximate results for planning and estimation purposes only. Actual requirements may vary based on site conditions, materials, workmanship, and local building regulations. Always consult a qualified engineer, architect, or construction professional before making final decisions.

FAQ

NEC Table 220.42(A) unit lighting loads by occupancy (default method), NEC Table 220.45 feeder/service demand factors, and NEC 220.46 show window/track lighting.
It covers common occupancy classifications directly, plus a Custom option for any occupancy not listed — enter your own NEC Table 220.42(A) VA/ft² figure.