Inputs
ℹ️Rectangular/Square uses Height x Width x Depth. Circular uses the circle area (pi x (Diameter/2)^2) x Height — a genuinely different formula, not just a relabeled rectangle.
Cost
Showing results for 4 columns
Concrete Volume
1.133 m³ / 40.0 cft
(0.283 m³ / 10.0 cft per column)
Total Wet Volume: 1.133 m³ / 40.0 cft
Dry Volume: 1.744 m³ / 61.6 cft
Sand: 0.476 m³ / 16.8 cft
Aggregate: 0.951 m³ / 33.6 cft
(Per column: Sand 0.119 m³ / 4.2 cft, Aggregate 0.238 m³ / 8.4 cft)
Cement Required
(Including 5% Wastage)
10 bags
(3 bags per column)
Extra (Wastage): 0.46 bags
Setting up column formwork for this pour? Column Formwork Process Guide →
Approximate results for planning only. Verify with a professional.
Looking for the verification checklist, reference tables, tips, or common mistakes?See the complete Concrete Column Calculator.
Column concrete volume
This page is useful when column dimensions are measured in feet and inches.
The calculator is pre-filled for this column use case. Edit any input and the worked example updates from the active values.
- Height: 10 ft.
- Column size: 12 x 12 in.
- Count: 4 columns.
How does the concrete column calculator work?
Wet volume depends on the column shape — Rectangular/Square uses the cross-section area (Width × Depth), while Circular uses the circle area instead. Every shape then follows the same dry-volume, mix-ratio, and wastage steps.
Step 1 — Rectangular / Square
Step 2 — Circular
Enter the diameter, not the radius — the formula already halves it.
Step 3 — Convert to Dry Volume
The 1.54 factor accounts for voids in aggregates, sand bulking, and material loss during mixing.
Step 4 — Split by Mix Ratio
Step 5 — Convert Cement Volume to Bags
Step 6 — Add Wastage
Step 7 — Cost (Optional)
All three quantities are priced at their wastage-adjusted amount — the quantity you'd actually order, not the theoretical minimum before wastage. Sand and aggregate prices can be entered per m³ or per cft — whichever unit you enter is converted to match the volume automatically.
Worked Example
This example uses the active inputs above and follows the same steps as the Formula section.
Input Values Used
| Input | Value |
|---|---|
| Column Type | Rectangular / Square Column |
| Height | 10 ft (3.048 m) |
| Width | 12 in (0.305 m) |
| Depth | 12 in (0.305 m) |
| Count | 4 |
| Concrete Mix | M20 (1:1.5:3) |
| Wastage | 5% |
Step 1 — Wet Volume
| Calculation | Substitution | Result |
|---|---|---|
| H × W × D × Count | 3.048 × 0.305 × 0.305 × 4 | 1.133 m³ / 40.0 cft |
Step 2 — Dry Volume
| Calculation | Substitution | Result |
|---|---|---|
| Dry Volume = Wet Volume × 1.54 | 1.133 × 1.54 | 1.744 m³ / 61.6 cft |
Step 3 — Materials & Cement Bags
| Material | Share of Mix (1:1.5:3) | Result |
|---|---|---|
| Sand | 1.5 / 5.5 | 0.476 m³ / 16.8 cft |
| Aggregate | 3 / 5.5 | 0.951 m³ / 33.6 cft |
| Cement Bags (with 5% wastage) | 1 / 5.5 | 10 bags |
Therefore, this rectangular / square column needs approximately 1.133 m³ / 40.0 cft of concrete, requiring 10 cement bags, 0.476 m³ / 16.8 cft sand, and 0.951 m³ / 33.6 cft aggregate (including 5% wastage on cement).
Cross-check against the Column Type & Mix Reference table in the complete Concrete Column Calculator.