TryBuildCalc

Circular Column Concrete Calculator (Rectangular & Circular — Volume, Cement, Sand & Aggregate)

Calculate column concrete volume and materials.

Inputs

ℹ️Rectangular/Square uses Height x Width x Depth. Circular uses the circle area (pi x (Diameter/2)^2) x Height — a genuinely different formula, not just a relabeled rectangle.

ℹ️Enter the diameter, not the radius — using the radius here would understate volume by a factor of 4.

Cost

Enable Cost Estimation?

Showing results for 4 columns

Concrete Volume

0.848/ 29.9 cft

(0.212 m³ / 7.5 cft per column)

Total Wet Volume: 0.848 m³ / 29.9 cft

Dry Volume: 1.306 m³ / 46.1 cft

Sand: 0.356 m³ / 12.6 cft

Aggregate: 0.713 m³ / 25.2 cft

(Per column: Sand 0.089 m³ / 3.1 cft, Aggregate 0.178 m³ / 6.3 cft)

Cement Required
(Including 5% Wastage)

8 bags

(2 bags per column)

Extra (Wastage): 0.34 bags

Setting up column formwork for this pour? Column Formwork Process Guide →

Approximate results for planning only. Verify with a professional.

Circular Column VisualizationH = 3 mD = 300 mmDiagram simplified for clarity (not to scale)

Looking for the verification checklist, reference tables, tips, or common mistakes?See the complete Concrete Column Calculator.

4 circular columns, 300 mm diameter x 3 m height

A circular column uses Volume = pi x (Diameter/2)^2 x Height — a genuinely different formula from a rectangular column, since it's based on the circle's area rather than width x depth. For 4 columns at 300 mm diameter and 3 m height, total wet volume is 0.848 m³, dry volume 1.306 m³, needing about 8 cement bags (1:1.5:3 mix, 5% wastage), 0.356 m³ sand, and 0.713 m³ aggregate.

The calculator is pre-filled for this column use case. Edit any input and the worked example updates from the active values.

  • Default column: 300 mm diameter x 3 m height.
  • Count: 4 columns.
  • ~8 cement bags with 5% wastage (1:1.5:3 mix).

How does the concrete column calculator work?

Wet volume depends on the column shape — Rectangular/Square uses the cross-section area (Width × Depth), while Circular uses the circle area instead. Every shape then follows the same dry-volume, mix-ratio, and wastage steps.

Step 1 — Rectangular / Square

Wet Volume = Height × Width × Depth × Count

Step 2 — Circular

Wet Volume = π × (Diameter / 2)² × Height × Count

Enter the diameter, not the radius — the formula already halves it.

Step 3 — Convert to Dry Volume

Dry Volume = Wet Volume × 1.54

The 1.54 factor accounts for voids in aggregates, sand bulking, and material loss during mixing.

Step 4 — Split by Mix Ratio

Cement = (Cement Ratio ÷ Total Ratio) × Dry Volume — same for Sand and Aggregate

Step 5 — Convert Cement Volume to Bags

Cement Bags = Cement Volume ÷ 0.0347

Step 6 — Add Wastage

Final Cement Bags = Calculated Bags × (1 + Wastage %)

Step 7 — Cost (Optional)

Total Cost = (Cement Bags × Price/Bag) + (Sand Volume × Price/Volume) + (Aggregate Volume × Price/Volume)

All three quantities are priced at their wastage-adjusted amount — the quantity you'd actually order, not the theoretical minimum before wastage. Sand and aggregate prices can be entered per m³ or per cft — whichever unit you enter is converted to match the volume automatically.

Worked Example

This example uses the active inputs above and follows the same steps as the Formula section.

Input Values Used

InputValue
Column TypeCircular Column
Height3 m (3 m)
Diameter300 mm (0.3 m)
Count4
Concrete MixM20 (1:1.5:3)
Wastage5%

Step 1 — Wet Volume

CalculationSubstitutionResult
π × (D / 2)² × H × Countπ × (0.3 / 2)² × 3 × 40.848 m³ / 29.9 cft

Step 2 — Dry Volume

CalculationSubstitutionResult
Dry Volume = Wet Volume × 1.540.848 × 1.541.306 m³ / 46.1 cft

Step 3 — Materials & Cement Bags

MaterialShare of Mix (1:1.5:3)Result
Sand1.5 / 5.50.356 m³ / 12.6 cft
Aggregate3 / 5.50.713 m³ / 25.2 cft
Cement Bags (with 5% wastage)1 / 5.58 bags

Therefore, this circular column needs approximately 0.848 m³ / 29.9 cft of concrete, requiring 8 cement bags, 0.356 m³ / 12.6 cft sand, and 0.713 m³ / 25.2 cft aggregate (including 5% wastage on cement).

Cross-check against the Column Type & Mix Reference table in the complete Concrete Column Calculator.

FAQ

A circular column's cross-section is a circle (pi x radius^2), not a rectangle (width x depth), so its volume formula genuinely differs: Volume = pi x (Diameter/2)^2 x Height x Count. Entering the radius instead of the diameter here understates volume by 4x.
Circular columns are common under a single steel column base, for decorative or architectural columns (porches, verandahs), and in some structural applications where a round section is specified on the drawing.