TryBuildCalc

Topsoil Removal Calculator Topsoil removal volume and truck-load estimator

Estimate topsoil removal volume, loose quantity, and haul-away truck loads.

Site Footprint

Multiple Different-Sized Sections?

ℹ️Length of the area to be stripped.

ℹ️Width of the area to be stripped.

ℹ️Set to more than 1 if several identical areas share this same footprint and stripping depth.

Stripping

ℹ️Confirm with test pits/soil cores rather than assuming — commonly 100-150 mm, but varies by site.

ℹ️Volume increase once topsoil is dug and loosened — commonly 15-25%.

ℹ️Used only for the informational weight estimate — does not affect volume unless the stripping rate below is priced per tonne.

ℹ️Share of loose topsoil stockpiled for on-site reuse (final landscaping/grading); the rest is treated as haul-away.

Stockpile Footprint

Estimate Stockpile Footprint?

Cost

Enable Cost Estimation?

ℹ️Applies to the full loose volume — the strip/handle operation happens whether the material is reused or hauled away.

ℹ️Used to convert the haul-away volume (the portion not reused) into truck loads.

ℹ️Applies only to the haul-away portion, not the reused/stockpiled volume.

ℹ️Optional buffer for unknowns — depth variability, wet conditions, or a change in reusable quantity. Commonly 5-15%.

For a 500.00 (5,382 sqft) site stripped 150 mm deep, you get approximately 90.00 (3,178.3 cft) of loose topsoil — 18.00 for reuse/stockpile and 72.00 to haul away.

Stripped Volume

Material: Loose / Friable Topsoil

In-situ (stripped) volume: 75.00 (2,648.6 cft)

Loose volume (with swell): 90.00 (3,178.3 cft)

99.00 tonnes at 1100 kg/m³

Reuse / Haul-Away Split

Reuse allowance: 20%

Reuse (stockpiled) volume: 18.00 (635.7 cft)

Haul-away volume: 72.00 (2,542.7 cft)

Truck loads (haul-away): 12

Stockpile Footprint

Stockpile footprint not estimated in this run.

Cost Summary

Stripping cost: 18,000

Haul-away cost (12 loads): 36,000

Total estimated cost: 54,000

Assumptions Used

Loose volume = in-situ (stripped) volume × (1 + swell%) | Reuse/haul-away split applies to loose volume | Stockpile modeled as a cone capped at the chosen side-slope ratio, extra volume needs extra piles at the same height | Weight is informational only and never affects volume/cost math.

Approximate results for planning only. Verify with a professional.

Topsoil Stripping Cross-Section

Existing ground levelTopsoil LayerLoose / Friable TopsoilStripped & removedFormation / subgrade levelDepth: 150 mmSite footprint: 25 m × 20 mStockpile (per pile)Turn on "EstimateStockpile Footprint?"to see this.Diagram simplified for clarity, not to scale.

Looking for the verification checklist, reference tables, or tips and mistakes?See the complete Topsoil Stripping Calculator.

Topsoil removal and haul-away estimate

This page is set up for a removal-focused scenario, where most of the stripped topsoil leaves the site rather than being reused: a 25 m x 20 m footprint (500 m²) at the default 150 mm depth gives 75 m³ in-situ, or 90 m³ loose after 20% swell — about 99 tonnes. With only a 20% reuse rate set here, 18 m³ stays on-site and 72 m³ is haul-away material.

That haul-away volume needs 12 truck loads at a 6 m³ truck capacity (ceil(72 ÷ 6) = 12), and with a 200/m³ stripping rate and 3,000/load haul rate, the combined stripping and haul-away cost comes to about 54,000.

  • Default footprint: 25 m x 20 m (500 m²), 20% reuse (most material hauled away).
  • Loose volume: 90 m³ → 72 m³ haul-away.
  • 12 truck loads, combined cost ~54,000.

How Is Topsoil Stripping Calculated?

The calculation happens in stages — stripping volume, swell, the reuse/haul-away split, optional stockpile footprint — then an optional cost estimate on top.

Step 1 — Stripping Area

Area = Length × Width

Total Area = Area × Number of Identical Sections

If sections differ in size: Total Area = Sum of (Length × Width × Count) for every section

The footprint is the area to be stripped. Number of Identical Sections multiplies the whole result for repeated areas of the same size; for areas of different sizes, switch on "Multiple Different-Sized Sections" and the calculator sums every row's area into one combined total automatically.

Step 2 — Stripped Volume & Swell

In-Situ (Stripped) Volume = Total Area × Stripping Depth

Loose Volume = In-Situ Volume × (1 + Swell %)

Topsoil expands once dug up and loosened — the swell/bulking percentage converts the in-situ (bank) volume into the loose volume you actually need to handle, stockpile, or truck away.

Step 3 — Reuse / Haul-Away Split

Reuse Volume = Loose Volume × Reuse %

Haul-Away Volume = Loose Volume − Reuse Volume

The reuse percentage is the share of loose topsoil stockpiled on-site for later landscaping or final grading; the remainder is treated as haul-away material that needs trucking off-site.

Step 4 — Stockpile Footprint (Optional)

Radius per Pile = Stockpile Height × Side Slope Ratio

Max Volume per Pile = ⅓ × π × Radius² × Height

Piles Needed = ROUND UP(Reuse Volume ÷ Max Volume per Pile)

Each stockpile is modeled as a cone at your chosen height, with its side slope capped at a gentle run-to-rise ratio (default 5:1) rather than a steep natural angle of repose — matching erosion-control practice for topsoil specifically. A reuse volume larger than one pile's capacity needs additional piles at the same height and slope.

Step 5 — Truck Loads & Cost

Truck Loads = ROUND UP(Haul-Away Volume ÷ Truck Capacity)

Stripping Cost = Loose Volume × Stripping Rate

Haul-Away Cost = Truck Loads × Rate per Load

Truck loads are based only on the haul-away volume, since the reused portion is stockpiled on-site rather than trucked out. The stripping rate applies to the full loose volume (stripping/handling happens either way), while the haul-away rate applies only to the trucked-away share.

Step 6 — Add Contingency (Optional)

Base Cost = Stripping Cost + Haul-Away Cost

Contingency Amount = Base Cost × (Contingency % ÷ 100)

Total Cost = Base Cost + Contingency Amount

Contingency is an optional buffer on top of the combined cost to cover unexpected variance — depth variability, wet conditions, or a change in how much is actually reusable once seen on site. It defaults to 0%; a commonly used range is 5-15%.

Worked Example

This example walks through your current inputs above, using the same steps as the Formula section. Each table shows the calculation, the values substituted in, and the result it produces.

Input Values Used

InputValueWhy it is used
Site footprint25 m × 20 m, 1 section(s)Sets the area the stripped volume is built on
Depth / material150 mm, Loose / Friable TopsoilSets in-situ volume and tonnage estimate
Swell / reuse20% swell, 20% reused on-siteConverts in-situ volume into loose volume, then splits it
Rates & contingency200 per stripping, 6 /truck, 3,000/loadSets stripping cost, truck loads, haul-away cost and total

Step 1 — Stripping Area

CalculationSubstitutionResult
Area25 m × 20 m500.000
Total area500.00 × 1500.000 m² (5,381.95 sqft)

Step 2 — Stripped Volume & Swell

CalculationSubstitutionResult
In-situ (stripped) volume500.00 m² × 150mm75.000
Loose volume (with swell)75.000 × 1.2090.000 m³ (3,178.3 cft)

Step 3 — Reuse / Haul-Away Split

CalculationSubstitutionResult
Reuse volume90.000 m³ × 20%18.000
Haul-away volume90.00018.00072.000 m³ (2,542.7 cft)

Step 5 & 6 — Truck Loads, Cost & Contingency

CalculationSubstitutionResult
Truck loads72.000 ÷ 6 12 loads
Stripping cost90.000 m³ × 200/m³18,000
Haul-away cost12 loads × 3,000/load36,000
Base costStripping + haul-away54,000
Total costBase cost54,000

Therefore, this 500.0 m² site needs approximately 90.00 of loose topsoil handled — 18.00 reused and 72.00 hauled away, costing around 54,000.

This page keeps things focused on the calculation above. For the full construction guide — verification checklist, reference tables, usage steps, tips, common mistakes, and limitations.See the complete Topsoil Stripping Calculator.

Related Calculators

FAQ

This page illustrates a site-clearance scenario where most stripped topsoil is genuinely surplus and needs removal — for example, a site where the finished landscaping plan only needs a small reserved quantity. Set the reuse percentage to match your actual site plan; it can range from near-zero for a fully cleared site to 90%+ for a site that keeps most of its topsoil.
Truck loads apply only to the haul-away volume (72 m³ here, since only that portion leaves the site), divided by the 6 m³ truck capacity: 72 ÷ 6 = 12 exactly, so 12 full truck loads are needed — a partial load would still round up to a full trip.