Inputs

Wall Geometry

ℹ️For walls above 1.5 m, use engineer-designed details.

ℹ️Rule of thumb: 1/8 of wall height, minimum 150 mm.

Wall Type & Material

Cap Row?
kg/m³

ℹ️Use 5–20%. Default 12% suits block retaining walls.

Backfill & Drainage

ℹ️Minimum 300 mm clean gravel behind the wall is commonly used.

Include Perforated Drain Pipe?
Include Geotextile Filter Fabric?
Weep Holes?

Advanced: Stability Check

Run Stability Check?

For engineers / technical use. Confirm with a structural engineer for walls above 1.5 m.

Cost Estimation

Enable Cost Estimation?

Wall Face Area

15.00

161.5 sq ft

Total Wall Height

1.65 m

incl. embedment

Wall Type

Gabion

Drainage Gravel

4.50

7.2 tonnes

Gabion Wall Materials

Gabion Box Size: 2 × 1 × 1 m

Number of Gabion Boxes: 8 nos.

Stone Fill Volume: 10.40

Stone Fill Weight: 16.64 tonnes

Wire Mesh Approx.: 80.00

Backfill & Drainage

Gravel Drainage Volume: 4.50 m³ / 158.9 cft

Gravel Weight for Ordering: 7.20 tonnes

Drain Pipe Length: 0.00 m

Geotextile Fabric Area: 0.00

Weep Holes: 0 nos.

Backfill Soil Volume: 10.50

Assumptions Used

Gravel density: 1600 kg/m³ | Mortar dry volume factor: 1.30 | Cement bag: 50 kg | Steel estimate: selected percentage × concrete volume × 7850 kg/m³.

Stability check assumes level, dry, cohesionless backfill and does not replace structural design.

Need to estimate the formwork for this poured concrete wall? Shuttering / Formwork Calculator →

Already seeing cracks in an existing retaining or compound wall? Wall Cracks: Causes and Remediation →

Retaining Wall Visualization

Backfill Soil4.5 m³ gravelRetained height: 1.5 mEmbedment: 0.15 mDrain layerWater drains downWall type: GabionDiagram simplified for clarity. Actual retaining wall design must follow project drawings and engineer instructions.

Looking for the verification checklist, reference tables, tips, or common mistakes?See the complete Retaining Wall Calculator.

Gabion retaining wall estimate

This page pre-selects gabion construction at 1.5 m retained height with standard 2×1×1 m boxes — a common size balancing ease of handling with fill efficiency.

Edit the wall length, height, or box size above and the gabion box count, stone fill volume, and weight update from the active values, still using gabion construction.

  • Gabion walls suit 1.0–3.0 m retained height with excellent inherent drainage, since the stone fill itself is naturally free-draining.
  • Stone fill volume uses a 65% fill factor to account for voids between stones — a planning estimate, not an exact packing figure.
  • Gabion is a good choice where a natural, flexible wall face is preferred over a rigid concrete or masonry finish.

How Is Retaining Wall Material Calculated?

The calculation starts from wall length and total height (retained height plus embedment), then works out material quantity by construction type, drainage system sizing, optional cost, and an optional simplified stability check.

Step 1 — Convert Dimensions to Metres and Find Total Wall Height

Wall Length, Wall Height, Embedment Depth (m) = Entered values converted to metres

Total Wall Height (m) = Wall Height (above ground) + Embedment Depth

Total wall height includes the embedded portion below finished ground level, so it is taller than the visible retained height — this total height drives course count, concrete volume, and the stability check.

Step 2 — Calculate Wall Face Area

Wall Face Area (m²) = Wall Length × Wall Height (above ground)

Wall face area uses only the visible retained height, not embedment, and is used for drainage gravel volume, geotextile area, RCC formwork, and labour cost.

Step 3 — Calculate Block Quantity (Dry-Stack or Mortared Block Walls)

Courses = CEIL(Total Wall Height ÷ (Block Height + Mortar Joint))

Blocks per Course = CEIL(Wall Length ÷ (Block Length + Mortar Joint))

Total Blocks = Courses × Blocks per Course

Cap Blocks = CEIL(Wall Length ÷ Cap Block Length), if a cap row is included

Blocks with Wastage = (Total Blocks + Cap Blocks) × (1 + Wastage % ÷ 100)

Mortar joint is zero for dry-stack block. Courses and blocks per course always round up, so the wall never falls short by a partial course or partial block.

Step 4 — Calculate Mortar, Cement & Sand (Mortared Block Walls Only)

As-Built Wall Volume (m³) = (Blocks per Course × (Block Length + Joint)) × (Courses × (Block Height + Joint)) × Block Width

Wet Mortar Volume (m³) = As-Built Wall Volume − (Total Blocks × Block Solid Volume)

Dry Mortar Volume (m³) = Wet Mortar Volume × 1.30

Cement (bags) = Dry Mortar Volume × [1 ÷ (1 + Sand Parts)] × 1440 kg/m³ ÷ 50 kg

Sand (m³) = Dry Mortar Volume × [Sand Parts ÷ (1 + Sand Parts)]

Wall volume is calculated from the as-built footprint (courses × blocks per course, including joint thickness) rather than the nominal wall length and height, since courses and blocks per course always round up. This step only applies to mortared block walls — dry-stack, poured concrete, and gabion walls do not use mortar between courses.

Step 5 — Calculate RCC Stem, Footing Concrete & Steel (Poured Concrete Walls Only)

Stem Concrete (m³) = Wall Length × Total Wall Height × Stem Thickness

Footing Concrete (m³) = Wall Length × Footing Width × Footing Thickness (if footing included)

Total Concrete (m³) = Stem Concrete + Footing Concrete

Reinforcement Steel (kg) ≈ Total Concrete × Selected Steel % × 7,850 kg/m³

Formwork Area (m²) = Wall Length × Total Wall Height × 2

Steel is an approximate percentage of concrete volume, not a bar-by-bar design. Actual reinforcement needs a moment and shear calculation from a structural engineer for walls above about 1.5 m.

Step 6 — Calculate Gabion Boxes & Stone Fill (Gabion Walls Only)

Gabion Boxes = CEIL[(Wall Face Area × Box Width) ÷ Box Volume]

Stone Fill Volume (m³) = Gabion Boxes × Box Volume × 65%

Stone Fill Weight (tonnes) = Stone Fill Volume × Stone Density ÷ 1000

Wire Mesh Area (m²) ≈ Gabion Boxes × 2 × (box surface area)

The 65% fill factor accounts for voids between stones — actual packing density varies with stone shape and size, so treat this as a planning estimate rather than an exact fill quantity.

Step 7 — Calculate Backfill Drainage

Gravel Volume (m³) = Wall Length × Wall Height × Gravel Thickness

Gravel Weight (tonnes) = Gravel Volume × 1,600 kg/m³ ÷ 1000

Drain Pipe Length (m) = Wall Length × 1.15 (15% allowance for outlets), if included

Geotextile Area (m²) = Wall Length × (Wall Height + 0.5), if included

Weep Holes = CEIL(Wall Length ÷ 1.5), if included

Backfill Soil Volume (m³) = Wall Length × Wall Height × (Backfill Width − Gravel Thickness)

Drainage sizing applies to every wall type. Skipping the gravel layer, geotextile, or weep holes is the single most common cause of retaining wall failure, since trapped water adds hydrostatic pressure the wall was never designed to resist.

Step 8 — Calculate Total Cost

Material Cost = Block/Concrete/Gabion Cost + Gravel Volume × Gravel Rate + Drain Pipe Length × Drain Pipe Rate

Labour Cost = Wall Face Area × Labour Rate

Total Cost = Material Cost + Labour Cost

Cost estimation is optional and uses the rates and currency you enter — the calculator does not assume any market price on its own.

Step 9 — Run Simplified Stability Check (Advanced, Optional)

Active Earth Pressure Coefficient: Ka = tan²(45° − φ ÷ 2)

Active Earth Force: Pa = 0.5 × Ka × γ × Total Height² + Ka × Surcharge × Total Height

Base Width (B) = MAX(Footing Width, Wall's Own Thickness for the Selected Construction Type)

Dry-Stack Batter Centroid Shift = (Batter per Course × (Courses − 1)) ÷ 2

FOS Overturning = Resisting Moment ÷ Overturning Moment (min. 1.5, preferred 2.0)

FOS Sliding = (μ × Total Vertical Force) ÷ Active Earth Force (min. 1.5, preferred 2.0)

Toe/Heel Bearing Pressure = (V ÷ B) × (1 ± 6e ÷ B); Eccentricity limit = B ÷ 6 (B ÷ 8 preferred)

Base width (B) uses the footing width if a footing is included, otherwise the wall's own thickness for its construction type — a dry-stack or mortared block wall uses its block width, a poured concrete wall uses its stem thickness, and a gabion wall uses its box width; it never picks up an unrelated field left over from a different construction type. For dry-stack walls, the Wall Batter input shifts the wall's weight centroid backward as each course steps back from the one below, modestly improving overturning resistance. This is a simplified Rankine-theory check for level, dry, cohesionless backfill — useful as an early planning indicator, not a substitute for a licensed structural engineer's design on walls above 1.5 m, sloped backfill, seismic zones, or heavy surcharge.

Real-World Retaining Wall Calculation Example

This example uses the active calculator inputs above and follows the same steps from the formula section. Each table shows the value used, the formula applied, and the result produced.

Input Values Used

InputValueWhy it is used
Wall length10.00 mSets blocks per course, drainage length, and cost
Wall height (above ground)1.50 mRetained height used for wall face area and stability
Embedment depth0.15 mAdded to wall height for total height and course count
Wall construction typeGabionSelects which material formula (Step 3, 4, 5, or 6) applies
Wastage12%Adds allowance for breakage and handling loss
Drainage gravel300 mm thickSets gravel volume and weight behind the wall
Drainage extrasNone selectedIncluded drainage components add their own quantity rows
Stability checkNot runDrives Ka, earth force, and factor-of-safety checks

Step 1 — Convert Dimensions and Find Total Wall Height

Wall height above ground and embedment depth add together to give the total wall height used for course count and concrete volume.

CalculationFormula / SubstitutionResult
Wall length10 m → m10.00 m
Wall height above ground1.5 m → m1.50 m
Embedment depth0.15 m → m0.15 m
Total wall height1.50 + 0.151.65 m

Step 2 — Wall Face Area

Wall face area uses the visible retained height only, and drives drainage gravel volume, geotextile area, and labour cost.

CalculationFormula / SubstitutionResult
Wall face area10.00 × 1.5015.00

Step 6 — Gabion Boxes & Stone Fill

Box count comes from wall face area and box size; stone fill volume applies a 65% fill factor for voids between stones.

CalculationFormula / SubstitutionResult
Gabion boxesCEIL[(15.00 × box width) ÷ box volume]8 boxes (2 × 1 × 1 m)
Stone fill volume8 × box volume × 65%10.40
Stone fill weight10.40 × 1600 ÷ 100016.64 tonnes
Wire mesh (approx.)8 × 2 × box surface area80.00

Step 7 — Backfill Drainage

Drainage sizing applies regardless of wall type — gravel volume comes from wall face area and gravel thickness, with drain pipe, geotextile, and weep holes added if selected.

CalculationFormula / SubstitutionResult
Gravel volume10.00 × 1.50 × 300 mm4.50
Gravel weight4.50 × 1,600 ÷ 10007.20 tonnes
Drain pipe lengthNot included0.00 m
Geotextile areaNot included0.00
Weep holesNot included0 nos.

Therefore, for a 10.00 m long, 1.50 m high Gabion retaining wall, you need 8 gabion boxes and 10.40 m³ of stone fill, plus 4.50 of drainage gravel.

Disclaimer: This calculator provides approximate results for planning and estimation purposes only. Actual requirements may vary based on site conditions, materials, workmanship, and local building regulations. Always consult a qualified engineer, architect, or construction professional before making final decisions.

FAQ

The stone fill inside gabion baskets is itself naturally free-draining, so gabion walls have inherently better drainage behaviour than a solid masonry or concrete wall — though this calculator still recommends the standard gravel/geotextile/weep-hole system behind the gabion baskets themselves for the retained soil side.
Stone fill packed into a gabion box doesn't fill 100% of the box volume — voids between irregularly shaped stones mean roughly 65% of the box volume ends up as solid stone. This factor converts gabion box volume into an estimated stone fill volume and weight for ordering.