TryBuildCalc

DPM Calculator for Floor Floor DPM roll quantity estimator

Calculate DPM roll quantity for a floor base, including overlap and wastage.

Plinth Footprint

Multiple Different-Sized Sections?

ℹ️Internal footprint length to be filled, from the foundation/plinth drawing.

ℹ️Internal footprint width to be filled.

ℹ️Set to more than 1 if several identical rooms/blocks share this same footprint and fill depth.

Fill Layer

ℹ️Height from formation level to the underside of the PCC bed; commonly 150-450 mm for residential plinths.

ℹ️Extra loose volume needed over the compacted volume — pre-filled per material, adjust if your supplier's data differs.

PCC Bed

ℹ️Commonly 50-100 mm for a residential floor base.

DPM (Damp-Proof Membrane)

Include DPM?

ℹ️Accounts for the minimum ~150mm lap required at every joint between sheets.

ℹ️Extra allowance for the upturn at edges/walls and offcuts.

Cost

Enable Cost Estimation?

For a 99.00 (1,066 sqft) plinth footprint filled 200 mm deep with soil / select fill, you need approximately 41.84 tonnes of fill material and 7.796 (275.3 cft) of PCC bed concrete.

Compacted Fill

Material: Soil / Select Fill

Compacted volume: 19.800 (699.2 cft)

Loose volume (before wastage): 22.770 (804.1 cft)

Loose volume (with wastage): 23.909 (844.3 cft)

Material to order: 41.84 tonnes

PCC Bed (1:4:8)

Thickness: 75 mm

Total concrete: 7.796 (275.32 cft)

Cement: 26.6 bags

Sand: 3.694 (130.5 cft)

Aggregate: 7.388 (260.9 cft)

DPM (Damp-Proof Membrane)

Area with laps/wastage: 108.90 (1,172.2 sqft)

Roll coverage: 120.00/roll

Rolls needed: 2

Assumptions Used

Fill: loose volume = compacted volume × (1 + compaction%), then wastage on top | PCC: dry volume factor 1.54, wastage applied to cement/sand/aggregate together | DPM: rolls = ceil(area × (1 + wastage%) ÷ (roll area × (1 − overlap%))) | Flooring/screed/tiling above the DPM is outside this calculator's scope — see Limitations.

Approximate results for planning only. Verify with a professional.

Unsure where the DPM should sit relative to the PCC bed? Plinth Filling Guide →

Plinth Filling Cross-Section

Formation levelCompacted FillSoil / Select FillPCC Bed (1:4:8)DPM (membrane)Finished floor level (flooring by others)Fill: 200 mm75 mmPlinth footprint: 11 m × 9 mDiagram simplified for clarity, not to scale.

Looking for the verification checklist, reference tables, or tips and mistakes?See the complete Plinth Filling Calculator.

DPM roll requirement estimate

This page has DPM switched on by default to show the roll-count workflow directly: an 11 m x 9 m footprint (99 m²) inflated by the default 10% DPM wastage allowance to 108.9 m² of final area to cover. With the default 30 m x 4 m roll size and a 10% overlap allowance at every joint, each roll's effective coverage drops to 108 m², so it takes 2 rolls to cover the area (ROUND UP(108.9 / 108) = 2).

The fill and PCC bed sections still calculate alongside the DPM using this page's footprint at the calculator's default 200 mm soil fill depth and 75 mm PCC bed — the DPM is the final layer laid over that PCC bed, before the floor slab is poured on top.

  • Default footprint: 11 m x 9 m (99 m²), DPM included.
  • Roll size 30 m x 4 m, 10% overlap, 10% wastage → 108.9 m² final area.
  • Result: 2 rolls needed.

How Is Plinth Filling Calculated?

The calculation happens in three parts — compacted fill, PCC bed, and DPM — then an optional cost estimate on top.

Step 1 — Footprint Area

Area = Length × Width

Total Area = Area × Number of Identical Sections

If sections differ in size: Total Area = Sum of (Length × Width × Count) for every section

The footprint is the internal area to be filled, taken from the foundation/plinth drawing. Number of Identical Sections multiplies the whole result for repeated rooms/blocks of the same size; for rooms of different sizes, switch on "Multiple Different-Sized Sections" and the calculator sums every row's area into one combined total automatically.

Step 2 — Compacted Fill

Compacted Volume = Total Area × Fill Depth

Loose Volume = Compacted Volume × (1 + Compaction %)

Loose Volume (with wastage) = Loose Volume × (1 + Wastage %)

Order Quantity (tonnes) = Loose Volume (with wastage) × Material Density ÷ 1000

Delivered fill material is loose and has more air voids than it will once compacted in place, so the compaction percentage inflates the compacted (finished) volume into the loose volume you actually need to order; wastage is then applied on top of that loose volume, and the resulting figure converts directly to a tonnage using the material's density — the same convention this site's Backfill and Aggregate Coverage calculators use. For "Custom Fill Material", the density you enter is used directly in this step instead of a preset figure.

Step 3 — PCC Bed

Wet Volume = Total Footprint Area × PCC Thickness

Dry Volume = Wet Volume × 1.54

Cement / Sand / Aggregate = Dry Volume split by mix ratio parts

Wastage % applied to cement bags, sand, and aggregate together

This uses the same footprint area as Step 1 (so it stays correct whether you're using a single footprint or several differently-sized sections) and the same PCC formula as this site's dedicated PCC Calculator — a thin, lean-mix concrete bed that gives a firm, level surface for the DPM and floor slab above, not a structural element in its own right.

Step 4 — DPM (Damp-Proof Membrane)

Final Area = Total Area × (1 + Wastage %)

Roll Coverage = Roll Length × Roll Width × (1 − Overlap %)

Rolls Needed = ROUND UP(Final Area ÷ Roll Coverage)

Wastage accounts for the edge upturn and offcuts, while the overlap percentage accounts for the minimum lap required at every joint between adjoining sheets so ground moisture can't find a path through.

Step 5 — Add Contingency (Optional)

Base Cost = Fill Cost + PCC Cost + DPM Cost

Contingency Amount = Base Cost × (Contingency % ÷ 100)

Total Cost = Base Cost + Contingency Amount

Contingency is an optional buffer on top of the combined base cost to cover unexpected variance — supplier rate changes, delivery charges, or material substitution. It defaults to 0%; a commonly used range is 5-15%.

Worked Example

This example walks through your current inputs above, using the same steps as the Formula section. Each table shows the calculation, the values substituted in, and the result it produces.

Input Values Used

InputValueWhy it is used
Plinth footprint11 m × 9 m, 1 section(s)Sets the area every layer's volume is built on
Fill material / depthSoil / Select Fill, 200 mmSets fill density and compacted volume
Compaction / wastage15% compaction, 5% wastageConverts compacted volume into the loose quantity to order
PCC bed75 mm, 1:4:8, 5% wastageSets PCC wet volume and cement/sand/aggregate split
DPM roll30 m × 4 m, 10% overlap, 10% wastageSets roll coverage area and rolls needed

Step 1 — Footprint Area

The footprint area is the base every layer above is built on — fill volume, PCC volume, and DPM area all scale directly from it.

CalculationSubstitutionResult
Area11 m × 9 m99.000
Total area99.00 × 199.000 m² (1,065.63 sqft)

Step 2 — Compacted Fill

The compacted volume is what the finished, settled fill will occupy. Compaction inflates that into the loose volume, wastage inflates it once more into the loose volume actually ordered, and that final volume converts directly into a tonnage using the material's density — the same figure the cost step below uses.

CalculationSubstitutionResult
Compacted volume99.00 m² × 200mm19.800
Loose volume19.800 m³ × 1.1522.770
Loose volume (with wastage)22.770 m³ × 1.0523.909 m³ (844.3 cft)
Order quantity23.909 m³ × 1750 kg/m³ ÷ 100041.84 tonnes

Step 3 — PCC Bed

The PCC bed volume comes from the same total footprint area as Step 1, not the fill's compacted volume — it's a separate, thin layer cast on top of the finished fill.

CalculationSubstitutionResult
Wet volume99.00 m² × 75mm7.425
With 5% wastage7.425 × 1.057.796 m³ (275.3 cft, 26.6 bags)

Step 4 — DPM

The DPM area is inflated by wastage first (for edge upturn and offcuts), then divided by each roll's effective coverage — the roll area reduced by the overlap needed at every lap joint.

CalculationSubstitutionResult
Final area99.00 × 1.10108.90
Roll coverage30m × 4m × 0.90108.00
Rolls neededROUND UP(108.90 ÷ 108.00)2 rolls

Step 5 — Cost & Contingency

CalculationSubstitutionResult
Enable cost estimation above to see fill, PCC, and DPM cost

Therefore, this 99.0 m² plinth needs approximately 41.84 tonnes of fill material, 7.796 of PCC bed concrete, and 2 rolls of DPM.

This page keeps things focused on the calculation above. For the full construction guide — verification checklist, reference tables, usage steps, tips, common mistakes, and limitations.See the complete Plinth Filling Calculator.

Related Calculators

FAQ

The 99 m² footprint is inflated by 10% wastage to 108.9 m² final area. Each roll (30 m x 4 m = 120 m²) loses 10% of its area to overlap at joints, leaving 108 m² of effective coverage per roll. 108.9 ÷ 108 = 1.008, rounded up to 2 rolls — even a tiny excess over one roll's coverage requires starting a second roll.
DPM wastage accounts for the membrane turning up the surrounding walls at the perimeter (to link with the wall damp-proof course) plus offcuts from trimming around penetrations, which typically consumes more extra material proportionally than the fill or PCC layers — 10% is the calculator's default DPM wastage versus 5% for fill and PCC.