Floor Screed Calculator (Cement & Sand for Flooring)
Estimate screed cement and sand instantly.
🕒 Last updated: August 23, 2026
Inputs
ℹ️Typical: 38-50 mm (bonded/unbonded), 65-75 mm (floating/underfloor heating)
Cost
For 9.00 m² of floor area, you need approximately 4 cement bags and 0.50 m³ of sand.
Screed Volume
Floor area: 9.00 m²
Wet volume: 0.450 m³
Dry volume (×1.33): 0.599 m³
Materials
Cement: 3.6 bags — buy 4 bags
Sand: 0.503 m³ (~0.80 metric tons)
Sand tonnage is approximate, using 1.6 tons/m³ average bulk density.
Order Summary — Theoretical vs. Order Quantity
| Material | Theoretical | Order Quantity |
|---|---|---|
| Cement | 3.5 bags | 4 bags (whole) |
| Sand | 0.479 m³ | 0.503 m³ |
Theoretical = before wastage. Order Quantity = after your 5.0% wastage allowance (cement rounded up to a whole bag).
Assumptions Used
Dry volume factor: 1.33 | Cement bag: 50 kg / 0.0347 m³ | Wastage applied once to cement bags and sand volume.
Bonded, unbonded, or floating — not sure which screed type applies here? Floor Screed Guide →
Tiling this floor once the screed has cured and dried? Tile Calculator →
Looking for the verification checklist, reference tables, tips, or common mistakes?See the complete Floor Screed Calculator.
General floor screed quantity estimate
This page gives the full combined screed result — area, wet and dry screed volume, cement bags, and sand — from one set of floor length, width, thickness, and mix ratio inputs.
It's the same calculator behind every other screed variant on this site, just without a specific scenario pre-selected — useful for a general screed estimate before finalizing the exact floor with your site engineer.
- Dry volume correction (×1.33) is applied before splitting into cement and sand.
- Supports the three common cement:sand ratios from 1:3 (heavy-duty) to 1:5 (light leveling).
- An optional per-material cost estimate can be turned on from the same form.
Floor Screed Formula: How Is Cement and Sand Quantity Calculated?
Screed quantity is calculated from floor area and thickness, converted into dry volume, then distributed according to the cement:sand mix ratio.
Step 1 — Floor Area & Wet Volume
Floor Area = Length × Width
Wet Volume = Floor Area × Screed Thickness
Floor area is the plan area to be screeded. Wet volume is the actual mixed-screed volume needed to cover that area at the specified thickness.
Step 2 — Dry Volume Correction
Dry Volume = Wet Volume × 1.33
The dry volume factor accounts for sand bulking, voids between materials, and practical construction losses during mixing and application. Screed uses 1.33 rather than concrete's 1.54 because it contains no coarse aggregate.
Step 3 — Mix Ratio Distribution
Cement Volume = Dry Volume × (Cement Part ÷ Total Parts)
Sand Volume = Dry Volume × (Sand Part ÷ Total Parts)
Dry screed volume is divided according to the selected cement:sand mix ratio — 1:3 (heavy-duty industrial), 1:4 (standard), or 1:5 (light leveling only). Total Parts is the sum of both ratio parts.
Step 4 — Cement Bags Conversion
Cement Bags = Cement Volume ÷ 0.0347 m³/bag (50 kg bags)
One standard cement bag (50 kg) occupies approximately 0.0347 cubic metres. This conversion translates calculated cement volume into practical material procurement quantities.
Step 5 — Final Quantity with Wastage
Final Cement Bags = Cement Bags × (1 + Wastage %), rounded up to a whole bag
Final Sand Volume = Sand Volume × (1 + Wastage %)
Wastage is applied to both cement bags and sand volume for the practical order quantity — shown separately from the theoretical pre-wastage figures in the result card.
Worked Example
This example walks through your current inputs above, using the same steps as the Formula section.
Input Values Used
| Input | Value | Why it is used |
|---|---|---|
| Length × width | 3m × 3m | Sets the floor area to be screeded |
| Thickness / mix ratio / wastage | 50mm, 1:4, 5% wastage | Sets wet volume and splits dry volume into cement/sand |
Step 1 — Area & Volume
| Calculation | Substitution | Result |
|---|---|---|
| Floor area | 3m × 3m | 9.00 m² |
| Wet volume | 9.00 × 50mm | 0.450 m³ |
| Dry volume | 0.450 × 1.33 | 0.599 m³ |
Step 2 — Cement & Sand
| Material | Theoretical | Order Quantity |
|---|---|---|
| Cement | 3.5 bags | 4 bags (whole) |
| Sand | 0.479 m³ | 0.503 m³ |
Therefore, for 9.00 m² of floor at 50mm screed thickness and a 1:4 mix, you need approximately 4 cement bags and 0.50 m³ of sand.
Related Calculators
Disclaimer: This calculator provides approximate results for planning and estimation purposes only. Actual requirements may vary based on site conditions, materials, workmanship, and local building regulations. Always consult a qualified engineer, architect, or construction professional before making final decisions.