Calculate dewatering volume and pump sizing for a basement excavation.

Excavation Footprint

Multiple Different-Sized Sections?

ℹ️Length of the excavation base.

ℹ️Width of the excavation base.

ℹ️Set to more than 1 if several identical pits share this same footprint and depth.

Depth & Water Table

ℹ️Total depth from existing ground level to the base of the excavation.

ℹ️Depth from ground level to the natural groundwater level — confirm on site, since it can be shallower or more seasonal than a regional assumption.

Seepage Estimate

ℹ️A rough planning-stage seepage estimate — confirm with a pumping test or geotechnical report for anything beyond a small, low-risk excavation.

Pump Sizing

ℹ️Rated discharge capacity of a single pump you plan to use, from its spec sheet.

ℹ️Common minimum is 1 standby pump equal to the largest duty pump — increase for higher-consequence sites.

ℹ️Groundwater seepage is continuous, so most sites pump 24 hours/day — reduce only if a sump buffer allows controlled intermittent pumping.

ℹ️How long the excavation needs to stay dewatered — typically tied to the foundation/structure work duration.

Cost

Enable Cost Estimation?

With 2.50 m of excavation below the water table, you need to remove approximately 375.00 (13,243.0 cft) of standing water initially, then keep pumping 0.75 LPS of ongoing seepage using 2 pump(s) (1 duty + 1 standby).

Standing Water

Depth below water table: 2.50 m

Initial volume to clear: 375.00 (13,243.0 cft)

Initial pump-down time: 20.8 hours

Seepage & Pumps

Method: Silty Sand / Medium Permeability

Seepage rate: 0.75 LPS (2.7 m³/hr, 12 GPM)

Duty pumps: 1 + Standby: 1

Total pumps on site: 2

Ongoing Operation

Operating hours/day: 24

Duration: 30 days

Daily pumped volume: 64.80

Total water over duration: 2,319.00 (81,894.8 cft)

Assumptions Used

Initial volume = area × depth below water table | Seepage rate is a rough planning estimate by soil permeability class (or your measured/custom rate) — not a substitute for a pumping test or geotechnical assessment | Duty pumps sized with 1 unit of margin (round-up), standby pumps added on top for redundancy | Cost excludes mobilization, discharge permits, and site-specific power supply.

Approximate results for planning only. Verify with a professional.

Dewatering Cross-Section

Ground levelWater TableSeepage zonePumped to dischargeSump & pumpExcavationdepth: 4.00 mWT depth:1.50 mExcavation footprint: 15 m × 10 mDiagram simplified for clarity, not to scale.

Looking for the verification checklist, reference tables, or tips and mistakes?See the complete Dewatering Calculator.

Basement excavation dewatering estimate

This page is set up for a basement excavation that goes 4 m deep with the water table at 1.5 m — a common scenario for a below-grade basement in an area with a moderately shallow water table. On the 15 m x 10 m footprint (150 m²), that's 2.5 m of depth below the water table, giving 375 m³ of standing water to clear initially once excavation reaches that level.

Using the default silty sand/medium permeability preset, the estimated seepage rate is 0.75 LPS (150 m² x 0.5 LPS per 100 m² ÷ 100). One 5 LPS duty pump easily covers that, plus 1 standby pump, so initial pump-down takes about 20.83 hours, and ongoing seepage at 24 hours/day operation adds up to 1944 m³ over the default 30-day duration.

  • Default footprint: 15 m x 10 m (150 m²), 4 m excavation, 1.5 m water table → 2.5 m below water table.
  • Initial volume: 375 m³. Seepage: 0.75 LPS (silty sand preset).
  • 1 duty + 1 standby pump. Pump-down: 20.83 hours. Ongoing: 1944 m³ over 30 days.

How Is Dewatering Calculated?

The calculation happens in stages — excavation area, standing water volume, seepage rate, pump sizing — then optional cost on top.

Step 1 — Excavation Area

Area = Length × Width

Total Area = Area × Number of Identical Sections

If sections differ in size: Total Area = Sum of (Length × Width × Count) for every section

The base area is what every downstream volume and seepage figure is built on. Number of Identical Sections multiplies the whole result for repeated pits of the same size; for pits of different sizes, switch on "Multiple Different-Sized Sections" and the calculator sums every row's area into one combined total automatically.

Step 2 — Depth Below Water Table & Initial Volume

Depth Below Water Table = MAX(0, Excavation Depth − Water Table Depth)

Initial Volume = Total Area × Depth Below Water Table

If the excavation doesn't reach the water table, this is zero and no dewatering is needed. Otherwise, the initial volume is the standing groundwater that floods in and needs to be pumped out once before work can begin.

Step 3 — Seepage Rate

Preset: Seepage Rate = Total Area × Permeability Rate (per 100 m²) ÷ 100

Custom: Seepage Rate = your measured/estimated rate, entered directly

The soil-permeability presets are rough, order-of-magnitude planning figures — real seepage depends on hydraulic gradient and soil layering that a simple area-based rule can't fully capture. Switch to "Custom / Measured Rate" once you have an actual pumping test or geotechnical report figure.

Step 4 — Pump Sizing

Duty Pumps = ROUND UP(Seepage Rate ÷ Pump Capacity)

Total Pumps = Duty Pumps + Standby Pumps

Duty pumps are sized to handle the full seepage rate with rounding up for margin. Standby pumps are added on top for redundancy — a duty pump failure during active dewatering can re-flood the excavation, so standby capacity is standard practice, not optional.

Step 5 — Pump-Down Time & Ongoing Operation

Initial Pump-Down Time = Initial Volume ÷ (Duty Pumps × Pump Capacity)

Daily Volume = Seepage Rate × Operating Hours per Day

Total Water Over Duration = Initial Volume + (Daily Volume × Duration)

Initial pump-down time is how long it takes to clear the standing water already in the excavation using only the duty pumps. After that, the same duty pumps keep running to handle ongoing seepage for the full dewatering duration.

Step 6 — Cost & Contingency (Optional)

Rental Cost = Total Pumps × Rental Rate per Pump per Day × Duration

Fuel Cost = Duty Pumps × Fuel Rate per Pump per Day × Duration

Total Cost = (Rental Cost + Fuel Cost) × (1 + Contingency % ÷ 100)

Rental cost applies to every pump on site (duty and standby both need to be rented and ready), while fuel/power cost applies only to the duty pumps actually running. Contingency is an optional buffer on top for unknowns — a higher-than-estimated seepage rate or schedule delays.

Worked Example

This example walks through your current inputs above, using the same steps as the Formula section. Each table shows the calculation, the values substituted in, and the result it produces.

Input Values Used

InputValueWhy it is used
Excavation footprint15 m × 10 m, 1 section(s)Sets the base area every volume/seepage figure is built on
Depth / water table4 m excavation, 1.5 m water tableSets depth below water table and initial volume
Seepage estimateSilty Sand / Medium PermeabilitySets the ongoing inflow rate to be pumped
Pumps & operation5 LPS/pump, 1 standby, 24 hrs/day, 30 daysSets duty/standby pump count, run-time, and duration

Step 1 — Excavation Area

CalculationSubstitutionResult
Area15 m × 10 m150.000
Total area150.00 × 1150.000 m² (1,614.59 sqft)

Step 2 — Depth Below Water Table & Initial Volume

CalculationSubstitutionResult
Depth below water table4.001.502.50 m
Initial volume150.00 m² × 2.50 m375.00 m³ (13,243.0 cft)

Step 3 — Seepage Rate

CalculationSubstitutionResult
Seepage rate150.00 m² × rate ÷ 1000.75 LPS (2.7 m³/hr, 12 GPM)

Step 4 — Pump Sizing

CalculationSubstitutionResult
Duty pumpsROUND UP(0.75 ÷ 5.00)1
Total pumps1 duty + 1 standby2

Step 5 — Pump-Down Time & Ongoing Operation

CalculationSubstitutionResult
Initial pump-down time375.00 m³ ÷ (1 × 5.00 LPS)20.8 hours
Daily volume0.75 LPS × 24 hrs64.80 m³/day
Total water over duration375.00 + (64.80 × 30)2,319.00 m³ (81,894.8 cft)

Step 6 — Cost & Contingency

CalculationSubstitutionResult
Enable cost estimation above to see rental and fuel cost

Therefore, this excavation needs approximately 375.00 pumped out initially, then 0.75 LPS of ongoing seepage handled by 2 pump(s).

This page keeps things focused on the calculation above. For the full construction guide — verification checklist, reference tables, usage steps, tips, common mistakes, and limitations.See the complete Dewatering Calculator.

Related Calculators

FAQ

2.5 m of depth below the water table (4 m excavation minus 1.5 m water table depth) over the 150 m² footprint gives 375 m³ of standing water that needs pumping out before basement work can begin.
The default 5 LPS pump capacity comfortably exceeds the estimated 0.75 LPS seepage rate — ceil(0.75 ÷ 5) = 1 duty pump — with 1 standby pump added for redundancy, giving 2 pumps total and 5 LPS of duty capacity.