TryBuildCalc

M20 Slab Concrete Calculator (RCC Volume, Cement, Sand & Aggregate)

Calculate slab concrete volume and materials.

Inputs

Multiple Sections (L-shaped / irregular slab)?

ℹ️Typical: 100–150 mm

Optional Deductions

Deduct staircase openings, ducts, lift shafts, or other voids from the slab area before calculating concrete volume.

Cost

Enable Cost Estimation?

Concrete Volume: 4.500/ 158.9 cft

Wet Volume: 4.500 m³ / 158.9 cft

Dry Volume: 6.930 m³ / 244.7 cft

Sand: 1.890 m³ / 66.7 cft

Aggregate: 3.780 m³ / 133.5 cft

Cement Required (Including 5% Wastage): 39 bags

Extra (Wastage): 1.82 bags

Planning the shuttering and prop layout for this slab? Slab Shuttering Process Guide →

Approximate results for planning only. Verify with a professional.

Concrete Slab VisualizationL = 6 mW = 5 mT = 150 mmDiagram simplified for clarity (not to scale)

Looking for the verification checklist, reference tables, tips, or common mistakes?See the complete Concrete Slab Calculator.

M20 slab material estimate

This page uses a 1:1.5:3 ratio commonly used for nominal M20-style concrete estimates.

The calculator is pre-filled for this slab use case. Edit any input and the worked example updates from the active values.

  • Mix: 1:1.5:3.
  • Default slab: 6 m x 5 m.
  • Includes cement bags.

How does the concrete slab calculator work?

The calculator follows standard civil engineering formulas to estimate concrete volume and material quantities step-by-step, from the net slab area down to cement bags.

Step 1 — Calculate Net Slab Area

Net Area = Σ(Section Length × Section Width × Count) − Σ(Opening Length × Opening Width)

For a single rectangular slab this is just Length × Width. Multiple Sections sums each rectangle (for L-shaped/irregular footprints); Optional Deductions subtracts any staircase, duct, or void areas.

Step 2 — Calculate Wet Volume

Wet Volume = Net Area × Thickness

Step 3 — Convert to Dry Volume

Dry Volume = Wet Volume × 1.54

The factor 1.54 accounts for voids, bulking of sand, and material losses during mixing.

Step 4 — Calculate Material Proportions

Cement = (Cement Ratio ÷ Total Ratio) × Dry Volume — same for Sand and Aggregate

Step 5 — Convert Cement Volume to Bags

Cement Bags = Cement Volume ÷ 0.0347

Step 6 — Add Wastage

Final Cement Bags = Calculated Bags × (1 + Wastage %)

Step 7 — Cost (Optional)

Total Cost = (Cement Bags × Price/Bag) + (Sand Volume × Price/Volume) + (Aggregate Volume × Price/Volume)

All three quantities are priced at their wastage-adjusted amount. Sand and aggregate prices can be entered per m³ or per cft — whichever unit you enter is converted to match automatically.

Worked Example: Concrete Slab Calculation

This example uses the active inputs above and follows the same steps as the Formula section.

Input Values Used

InputValue
Length × Width6 m × 5 m = 30
Thickness150 mm (0.15 m)
Concrete MixM20 (1:1.5:3)
Wastage5%

Step 1 — Net Area & Wet Volume

CalculationSubstitutionResult
Net Area = Gross − Openings30030
Wet Volume = Net Area × Thickness30 × 0.154.5 m³ / 158.9 cft

Step 2 — Dry Volume

CalculationSubstitutionResult
Dry Volume = Wet Volume × 1.544.5 × 1.546.93 m³ / 244.7 cft

Step 3 — Materials & Cement Bags

MaterialShare of Mix (1:1.5:3)Result
Sand1.5 / 5.51.89 m³ / 66.7 cft
Aggregate3 / 5.53.78 m³ / 133.5 cft
Cement Bags (with 5% wastage)1 / 5.539 bags

Therefore, this slab needs approximately 4.5 m³ / 158.9 cft of concrete, requiring 39 cement bags, 1.89 m³ / 66.7 cft sand, and 3.78 m³ / 133.5 cft aggregate (including 5% wastage on cement).

Cross-check against the Standard Concrete Mix Ratios table in the complete Concrete Slab Calculator.

FAQ

This page is pre-filled for M20 slab concrete calculator so you can estimate slab concrete volume, cement bags, sand, aggregate, and wastage.
Yes. You can edit length, width, thickness, units, mix ratio, and wastage.