For 1.07 of masonry, you need approximately 2 cement bags and 0.29 of sand.

Mortar Volume

Masonry volume: 1.068

Wet mortar volume (~23% of masonry): 0.246

Dry volume (×1.33): 0.327

Materials

Cement: 1.7 bags — buy 2 bags

Sand: 0.286 (~0.46 metric tons)

Sand tonnage is approximate, using 1.6 tons/m³ average bulk density.

Order Summary — Theoretical vs. Order Quantity

MaterialTheoreticalOrder Quantity
Cement1.6 bags2 bags (whole)
Sand0.2720.286

Theoretical = before wastage. Order Quantity = after your 5.0% wastage allowance (cement rounded up to a whole bag).

Assumptions Used

Mortar volume: ~23% of masonry volume | Dry volume factor: 1.33 | Cement bag: 50 kg / 0.0347 m³ | Wastage applied once to cement bags and sand volume.

Need brick or block counts with door/window opening deductions? Wall / Masonry Calculator →

Plastering this wall after masonry work? Cement Plaster Calculator →

Mortar Wall VisualizationGrey area represents mortar jointsLength: 10 ftHeight: 10 ftThickness: 115 mmDiagram simplified for clarity (not to scale)

Looking for the verification checklist, reference tables, tips, or common mistakes?See the complete Mortar Calculator.

100 sq ft wall mortar quantity

A 10 ft × 10 ft wall is a common reference size for quick mortar quantity comparisons — this page is pre-filled to that size.

Edit the Wall Thickness or Mortar Mix Ratio above to match your actual wall, and the material breakdown updates from the active values.

  • Wall area: 100 sq ft (9.29 m²) before thickness is applied.
  • Default mix: 1:5 standard brickwork.
  • Scale this reference proportionally for larger or smaller wall areas.

Mortar Formula: How Is Cement and Sand Quantity Calculated?

Mortar quantity is estimated as a percentage of total masonry volume, then converted into dry volume and distributed according to the cement:sand mix ratio.

Step 1 — Masonry & Mortar Volume

Masonry Volume = Wall Length × Wall Height × Wall Thickness

Wet Mortar Volume ≈ Masonry Volume × 0.23

Masonry volume is the total volume of brickwork including bricks and mortar joints. In standard brick masonry, mortar joints occupy approximately 20% to 25% of total masonry volume — commonly approximated as 23% in estimation practice.

Step 2 — Dry Volume Correction

Dry Volume = Wet Mortar Volume × 1.33

The dry volume factor accounts for sand bulking, voids between materials, and practical construction losses during mixing and application. Mortar uses 1.33 rather than concrete's 1.54 because it contains no coarse aggregate.

Step 3 — Mix Ratio Distribution

Cement Volume = Dry Volume × (Cement Part ÷ Total Parts)

Sand Volume = Dry Volume × (Sand Part ÷ Total Parts)

Dry mortar volume is divided according to the selected cement:sand mix ratio — 1:3 (rich, structural), 1:4 (strong brickwork), 1:5 (standard brickwork), or 1:6 (light masonry). Total Parts is the sum of both ratio parts.

Step 4 — Cement Bags Conversion

Cement Bags = Cement Volume ÷ 0.0347 m³/bag (50 kg bags)

One standard cement bag (50 kg) occupies approximately 0.0347 cubic metres. This conversion translates calculated cement volume into practical material procurement quantities.

Step 5 — Final Quantity with Wastage

Final Cement Bags = Cement Bags × (1 + Wastage %), rounded up to a whole bag

Final Sand Volume = Sand Volume × (1 + Wastage %)

Wastage is applied to both cement bags and sand volume for the practical order quantity — shown separately from the theoretical pre-wastage figures in the result card.

Worked Example

This example walks through your current inputs above, using the same steps as the Formula section.

Input Values Used

InputValueWhy it is used
Length × height × thickness10ft × 10ft × 115mmSets the total masonry volume
Mix ratio / wastage1:5, 5% wastageSplits dry mortar volume into cement/sand and adds a buffer for site losses

Step 1 — Masonry & Mortar Volume

CalculationSubstitutionResult
Masonry volume10ft × 10ft × 115mm1.068
Wet mortar volume1.068 × 0.230.246
Dry volume0.246 × 1.330.327

Step 2 — Cement & Sand

MaterialTheoreticalOrder Quantity
Cement1.6 bags2 bags (whole)
Sand0.2720.286

Therefore, for 1.07 m³ of masonry at a 1:5 mix, you need approximately 2 cement bags and 0.29 of sand.

Disclaimer: This calculator provides approximate results for planning and estimation purposes only. Actual requirements may vary based on site conditions, materials, workmanship, and local building regulations. Always consult a qualified engineer, architect, or construction professional before making final decisions.

FAQ

100 square feet is a round, easy-to-scale number — once you know the mortar and cement quantity for a 100 sq ft wall at your chosen thickness and mix, you can estimate larger or smaller walls proportionally.
Feet — a 10 ft × 10 ft wall, giving 100 sq ft (about 9.29 m²) before wall thickness is applied to get masonry volume. Switch the unit selector for metric input if you prefer.